In: Statistics and Probability
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration.
Activity |
Follows |
|
A |
-- |
3 |
6 |
15 |
B |
A |
8 |
14 |
26 |
C |
A |
1 |
2 |
9 |
D |
B |
2 |
5 |
14 |
E |
C |
5 |
7 |
21 |
F |
D |
2 |
4 |
12 |
G |
B, E |
6 |
9 |
18 |
H |
F |
1 |
3 |
5 |
I |
D, G |
2 |
3 |
10 |
J |
G | 5 |
7 |
15 |
a) Calculate mean duration and standard deviation for all
activities using the beta distribution. (4 points)
b) Construct a network diagram for this problem using the mean
durations calculated in part (a), calculate the ES (Prec.),
LS(Foll.) and the total float for all the activities, and hence
identify the critical path . What is the mean completion time for
the project? What is the standard deviation of the critical path?
(3 0 points)
c) What is the 99% confidence interval for the length of the
critical path? (4 points)
d) Assuming that the probability distribution of the length of the
critical path can be approximated by a normal distribution with the
mean and standard deviation calculated in part (b), calculate the
probability of completing the project within 34 days . (4
points)
e) What is the probability that the project will be completed
between 38 and 45 days? Show your workings! (4 points)
f) Answer the project manager’s question:
“I want to tell the client a project length which I am 89.97% sure
that we can meet - What figure should I give them?" (4
points)