Question

In: Statistics and Probability

The following table lists the activities needed to complete a project. The first column lists the...

The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration.

Activity

Follows

Estimates of durations (days)

Optimistic

Most likely

Pessimistic

A

--

3

6

15

B

A

8

14

26

C

A

1

2

9

D

B

2

5

14

E

C

5

7

21

F

D

2

4

12

G

B, E

6

9

18

H

F

1

3

5

I

D, G

2

3

10

J

G 5

7

15

a) Calculate mean duration and standard deviation for all activities using the beta distribution. (4 points)
  
b) Construct a network diagram for this problem using the mean durations calculated in part (a), calculate the ES (Prec.), LS(Foll.) and the total float for all the activities, and hence identify the critical path . What is the mean completion time for the project? What is the standard deviation of the critical path? (3 0 points)
  
c) What is the 99% confidence interval for the length of the critical path? (4 points)
  
d) Assuming that the probability distribution of the length of the critical path can be approximated by a normal distribution with the mean and standard deviation calculated in part (b), calculate the probability of completing the project within 34 days . (4 points)
  
e) What is the probability that the project will be completed between 38 and 45 days? Show your workings! (4 points)
  
f) Answer the project manager’s question:
“I want to tell the client a project length which I am 89.97% sure that we can meet - What figure should I give them?" (4 points)

Solutions

Expert Solution


Related Solutions

The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
The table below defines number of working activities needed to accomplish a House project. The relationships...
The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type. Dependency Duration in days I.D Activity name ................................ 20 A Excavation work A 5 B Plain concrete work A 6 C Reinforced concrete work B & C 2 D Install grass C 10 E Build walls E 8 F Build roof E 7 G Plaster work F & G...
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
Assume that the transactions listed in the first column of the following table are anticipated by...
Assume that the transactions listed in the first column of the following table are anticipated by U.S. firms that have no other foreign transactions. Place an “X” in the table wherever you see possible ways to hedge each of the transactions.             1.   Georgetown Co. plans to purchase Japanese goods denominated in yen.             2   Harvard, Inc., sold goods to Japan, denominated in yen 3.   Yale Corp. has a subsidiary in Australia that will be remitting funds to...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
Skills needed to complete this assignment: linked lists, stacks. Postfix notation, is a mathematical notation in...
Skills needed to complete this assignment: linked lists, stacks. Postfix notation, is a mathematical notation in which operators follow their operands; for instance, to add 3 and 4, one would write 3 4 + rather than 3 + 4 (infix notation). If there are multiple operations, operators are given immediately after their second operands; so, the expression written 3 − 4 + 5 in conventional notation would be written 3 4 − 5 + in postfix notation: 4 is first...
The table lists heights (in.) of fathers and the heights (in.) of their first sons. Height...
The table lists heights (in.) of fathers and the heights (in.) of their first sons. Height of father (x) 73.0 75.5 75.0 75.0 75.0 74.0 74.0 73.0 73.0 78.5 Height of first son (y) 74.0 73.5 71.0 70.5 72.0 76.5 74.0 71.0 72.0 73.2 Find the linear correlation coefficient r Predict the height of a father whose first son measures 77 in.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT