Question

In: Operations Management

The following table lists the components needed to assemble an end item, lead times (in weeks),...

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

Item Lead Time Amount
on Hand
Direct Components
End 3 0 L(2), C(1), K(3)
L 3 12 B(2), J(3)
C 4 16 G(2), B(2)
K 4 21 H(4), B(2)
B 3 26
J 4 33
G 4 4
H 3 0


a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)

Additional units            

Solutions

Expert Solution

Answer: 434

Gross Requirement = Total no. units required (irrespective to On hand Inventory)

Net Requirement = Gross Requirement - Amount On Hand

Item B is required for Item L,C and K,

So, to derive the no. of additional unit of B, first we need to find the Gross Requirement of B, which is depend on the Net Requirement of L,C and K

Now Gross Requirement of L,C and K is depend on the end item, because they are direct components to End Item.

Gross Requirement of L = 2* Units of End item to be assembled = 2*43 = 86

Net Requirement of L = Gross Requirement of L - Amount On Hand of L = 86 - 12 =74

Gross Requirement of C = 1* Units of End item to be assembled = 1*43 = 43

Net Requirement of C = Gross Requirement of C- Amount On Hand of C= 43 - 16 =27

Gross Requirement of K = 3* Units of End item to be assembled = 3*43 = 129

Net Requirement of K= Gross Requirement of K- Amount On Hand of K= 129 - 21 = 108

Gross Requirement of B = 2*Net Requirement of L + 2*Net Requirement of C + 2*Net Requirement of K = 2*74 + 2*27 + 2*129 = 148 + 54 + 258 = 460

Net Requirement of B = Gross Requirement of B - Amount on Hand of B = 460 - 26 =434

So, additional 434 units of B are needed.


Related Solutions

The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 2 2 2 2 2 2 Amount on hand 0 8 11 23 9 28 6 0 a. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for 40 secondary school students in country A. A second selection of usual travel times to​ school, in​ minutes, was randomly selected for 40 students in country B. Complete parts​ a) and​ b). Sample Country A   Sample Country B 45   29 5   10 4   9 14   30 50   5 21   8 21   7 19   15 21   10 21   36 24   16 36   10 14   24...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he recorded while riding five laps through each mile of a 3-mile loop. Use a .05 significance level to test the claim that is takes the same time to ride each of the miles. Mile 1 3:15 3:25 3:23 3:22 3:22 Mile 2 3:19 3:23 3:20 3:17 3:19 Mile 3 3:34 3:30 3:29 3:30 3:29 Determine the null and alternate hypotheses. Find the F statistic...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT