Question

In: Operations Management

The table below defines number of working activities needed to accomplish a House project. The relationships...

The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type.

Dependency

Duration in days

I.D

Activity name

................................

20

A

Excavation work

A

5

B

Plain concrete work

A

6

C

Reinforced concrete

work

B & C

2

D

Install grass

C

10

E

Build walls

E

8

F

Build roof

E

7

G

Plaster work

F & G

9

H

Painting work

1) Construct schedule network diagram?

2) Analyze the early time schedule on the network diagram (use forward pass)

3) Analyze the late time schedule on the network diagram (use backward pass)

4) Calculate the "free float" for each activity and mark it down on the diagram.

5) locate the critical path and name it, determine the entire time of the project.

Solutions

Expert Solution

(Note: please like the answer it will encourage me. Do comment if any correction required before disliking.)


Related Solutions

13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $3,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using ES times. The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor...
Using the matrix below, summarize the practical knowledge, skills and behavior needed to accomplish each of...
Using the matrix below, summarize the practical knowledge, skills and behavior needed to accomplish each of the step in the Nutrition Care Process. answer what knowledge, skill and behavior or attitude need in the given steps in NUTRITION CARE PROCESS Steps in Nutrition Care Process Knowledge Needed Skills Needed Behavior/Attitude Needed Nutrition Assessment Nutrition Diagnosis Nutrition Intervention Nutrition Monitoring and Evaluation
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
In Hamilton county, ohio, the mean number of days needed to sell a house is 86...
In Hamilton county, ohio, the mean number of days needed to sell a house is 86 days (cincinnati Multiple listing Service, april, 2012). data for the sale of 40 houses in a nearby county showed a sample mean of 80 days with a sample standard deviation of 20 days. We want to do a hypothesis test to determine whether the mean number of days until a house is sold is different than the Hamilton county mean of 86 days in...
when the Sydney Opera house project was in progress, the organization which was working for this...
when the Sydney Opera house project was in progress, the organization which was working for this project had to face some issues such as internal communication issues and unavailability of the project manager. So explain completely about what these issues were and how the organization solved these two issues? Explain accurately and completely and in two paragraphs. Assignment is due on 2nd April at 12p.m.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT