Question

In: Operations Management

The table below defines number of working activities needed to accomplish a House project. The relationships...

The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type.

Dependency

Duration in days

I.D

Activity name

................................

20

A

Excavation work

A

5

B

Plain concrete work

A

6

C

Reinforced concrete

work

B & C

2

D

Install grass

C

10

E

Build walls

E

8

F

Build roof

E

7

G

Plaster work

F & G

9

H

Painting work

1) Construct schedule network diagram?

2) Analyze the early time schedule on the network diagram (use forward pass)

3) Analyze the late time schedule on the network diagram (use backward pass)

4) Calculate the "free float" for each activity and mark it down on the diagram.

5) locate the critical path and name it, determine the entire time of the project.

Solutions

Expert Solution

(Note: please like the answer it will encourage me. Do comment if any correction required before disliking.)


Related Solutions

13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $3,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using ES times. The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor...
Using the matrix below, summarize the practical knowledge, skills and behavior needed to accomplish each of...
Using the matrix below, summarize the practical knowledge, skills and behavior needed to accomplish each of the step in the Nutrition Care Process. answer what knowledge, skill and behavior or attitude need in the given steps in NUTRITION CARE PROCESS Steps in Nutrition Care Process Knowledge Needed Skills Needed Behavior/Attitude Needed Nutrition Assessment Nutrition Diagnosis Nutrition Intervention Nutrition Monitoring and Evaluation
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
In Hamilton county, ohio, the mean number of days needed to sell a house is 86...
In Hamilton county, ohio, the mean number of days needed to sell a house is 86 days (cincinnati Multiple listing Service, april, 2012). data for the sale of 40 houses in a nearby county showed a sample mean of 80 days with a sample standard deviation of 20 days. We want to do a hypothesis test to determine whether the mean number of days until a house is sold is different than the Hamilton county mean of 86 days in...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
The table below contains the value of the house and the amount of rental income in...
The table below contains the value of the house and the amount of rental income in a year that the house brings in ("Capital and rental," 2013). Table: Data of House Value versus Rental Value Rental Value Rental Value Rental Value Rental 81000 6656 77000 4576 75000 7280 67500 6864 95000 7904 94000 8736 90000 6240 85000 7072 121000 12064 115000 7904 110000 7072 104000 7904 135000 8320 130000 9776 126000 6240 125000 7904 145000 8320 140000 9568 140000 9152...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT