Question

In: Operations Management

The following table lists the components needed to assemble an end item, lead times, and quantities...

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.

Item End B C D E F G H
LT (wk) 2 2 2 2 2 2 2 2
Amount on hand 0 8 11 23 9 28 6 0

a. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)

Additional units            

b. An order for the end item is scheduled to be shipped at the start of week 14. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

The latest week            

Solutions

Expert Solution

Each unit requires item (B, C and D) and E is require in B,C and D items.

So to find the value of E we have to determine the net requirements for B, C and D

Now end unit requires 2 B’s

And units to be assembled is 22

Amount on Hand = 8

B = 22 * 2 = 40

B = 44 – amount on hand

B = 44 – 8

B = 36

End unit needed 1 unit of C

Units to be assembled = 22

Amount on hand = 11

C = 22* 1

C = 22

C = 22 – Amount on hand

C = 22 – 11

C = 11

End units requires 3 units of D’s

Unit to be assembled = 22

Amount on hand = 23

D = 22 * 3

D = 66

D = 66 – Amount on Hand

D = 66 – 23

D = 43

Answer A

Unit needed for E = (B * 2) + (C * 2) + (D * 2) - Amount on Hand of E

E = (36 * 2) + (11*2) + (43 * 2) - 9

E = 72 + 22 + 86 - 9

E = 180 - 9

E = 171

so 171 units of E is needed

Answer B

There are three sections that need to be complete in order for the end item to be complete i.e.

(1) B, E, and F

(2) C, G, and E,

(3) D, H and E

1. B week + E week + F week

2 + 2 +2 = 6

2. C weeks + G weeks + E weeks

2 + 2 + 2 = 6

3. D weeks + H weeks + E weeks

2 + 2 + 2 = 6

Latest  week = Start of week - 6 weeks

= 14 - 6

Latest week = 8


Related Solutions

The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 1 3 4 4 2 1 2 1 Amount on hand 0 10 9 25 11 29 6 0 End Item B(2)   C D(3) E(2) / F(3) G(2) / E(2) H(4) / E(2) a. If 20 units of the end item are to be assembled, how many additional units of E...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 16 G(2), B(2) K 4 21 H(4), B(2) B 3 26 J 4 33 G 4 4 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 14 G(2), B(2) K 3 20 H(4), B(2) B 2 31 J 3 28 G 3 4 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT