Question

In: Operations Management

The following table lists the components needed to assemble an end item, lead times, and quantities...

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.

Item End B C D E F G H
LT (wk) 2 2 2 2 2 2 2 2
Amount on hand 0 8 11 23 9 28 6 0

a. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)

Additional units            

b. An order for the end item is scheduled to be shipped at the start of week 14. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

The latest week            

Solutions

Expert Solution

Each unit requires item (B, C and D) and E is require in B,C and D items.

So to find the value of E we have to determine the net requirements for B, C and D

Now end unit requires 2 B’s

And units to be assembled is 22

Amount on Hand = 8

B = 22 * 2 = 40

B = 44 – amount on hand

B = 44 – 8

B = 36

End unit needed 1 unit of C

Units to be assembled = 22

Amount on hand = 11

C = 22* 1

C = 22

C = 22 – Amount on hand

C = 22 – 11

C = 11

End units requires 3 units of D’s

Unit to be assembled = 22

Amount on hand = 23

D = 22 * 3

D = 66

D = 66 – Amount on Hand

D = 66 – 23

D = 43

Answer A

Unit needed for E = (B * 2) + (C * 2) + (D * 2) - Amount on Hand of E

E = (36 * 2) + (11*2) + (43 * 2) - 9

E = 72 + 22 + 86 - 9

E = 180 - 9

E = 171

so 171 units of E is needed

Answer B

There are three sections that need to be complete in order for the end item to be complete i.e.

(1) B, E, and F

(2) C, G, and E,

(3) D, H and E

1. B week + E week + F week

2 + 2 +2 = 6

2. C weeks + G weeks + E weeks

2 + 2 + 2 = 6

3. D weeks + H weeks + E weeks

2 + 2 + 2 = 6

Latest  week = Start of week - 6 weeks

= 14 - 6

Latest week = 8


Related Solutions

The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for 40 secondary school students in country A. A second selection of usual travel times to​ school, in​ minutes, was randomly selected for 40 students in country B. Complete parts​ a) and​ b). Sample Country A   Sample Country B 45   29 5   10 4   9 14   30 50   5 21   8 21   7 19   15 21   10 21   36 24   16 36   10 14   24...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he recorded while riding five laps through each mile of a 3-mile loop. Use a .05 significance level to test the claim that is takes the same time to ride each of the miles. Mile 1 3:15 3:25 3:23 3:22 3:22 Mile 2 3:19 3:23 3:20 3:17 3:19 Mile 3 3:34 3:30 3:29 3:30 3:29 Determine the null and alternate hypotheses. Find the F statistic...
The following table lists the month-end prices from May 2017 to July 2018 of the Spider...
The following table lists the month-end prices from May 2017 to July 2018 of the Spider S&P 500 Index ETF (SPY) and iShares 20+ Treasury Bond ETF (TLT), respectively. During this time period the average annual yield for the one-month Treasury bills is 1.292% or 0.1077% per month. Apply the following equation to calculate the monthly returns from June 2017 to July 2018 for SPY and TLT, respectively. The monthly return for month n: rn = (Current month-end price –...
The table below lists the prices and quantities consumed of three different goods from 2014−2016. 2014...
The table below lists the prices and quantities consumed of three different goods from 2014−2016. 2014 2015 2016 Good Price ($) Quantity Price ($) Quantity Price ($) Quantity A 12 8 16 6 18 5 B 5 18 3 30 4 25 C 1 10 2 5 5 10 a. For 2014, 2015, and 2016, determine the amount that a typical consumer pays each year to purchase the quantities listed in the table above. Instructions: Round your answers to the...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded while riding a bicycle. He recorded every time he rode and randomly picked five laps through each mile of a​ 3-mile loop. Use a .05 significance level to test the claim that it takes the same time to ride each of the miles. Mile 1 194 205 203 202 201 Mile 2 198 201 200 196 200 Mile 3 215 211 209 212 209...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT