Question

In: Statistics and Probability

The expected times and variances for the project activities are given below. Complete the table showing...

The expected times and variances for the project activities are given below. Complete the table showing which activities are critical.

ID Description Predecessor Te Variance Critical?
1 Pilot Production None 6 3 ?
2 Select Channels of Distribution None 20 4 ?
3

Develope Mktg. Program

None 18 2 ?
4 Test Market 1 4 2 ?
5 Patent 1 17 5 ?
6 Full production 4 9 10 ?
7 Ad Promotion 3 16 2 ?
8 Release 2,5,6,7 2 1 ?

What is the probability of completing the project in 27 periods? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Do not round intermediate calculations. Round the final answer to 3 decimal places, i.e., 0.750.)

1). What is the probability of completing the project in 27 time periods?_____

***PLEASE SHOW ALL WORK! I AM TRYING TO LEARN :)***

Solutions

Expert Solution

Solution:
To fin Critical path and duration of project, we will create Network diagram, forward and backward pass

From the forward and backward pass, we found that critical path is 3-7-8 with critical time (18+16+2) = 36
Critical activities are those activities which have zero slack. So Critical activities are 3, 7 and 8

ID

Te

Variance

Critical?

1

6

3

No

2

20

4

No

3

18

2

Yes

4

4

2

No

5

17

5

No

6

9

10

No

7

16

2

Yes

8

2

1

Yes

We need to calculate probability that the project will complete in 27 periods
Critical time = 36 periods
Variance = (2+2+1) = 5 periods
Standard deviation = sqrt(5) = 2.24
Z-score = (X-mean)/Standard deviation = (27-36)/2.24 = -4.02
From normal distribution table we found p-value
P(X<=27 periods) = 0.000029
So there is 0.003% probability of completing the project in 27 periods.


Related Solutions

An IT project requires 6 activities. The table below displays the expected time and budgeted cost...
An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $3,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using ES times. The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor...
1. Complete the table given showing the costs of a perfectly competitive firm.
1. Complete the table given showing the costs of a perfectly competitive firm.OutputTotal CostTotal Fixed CostTotal Variable CostAverage Fixed CostAverage Variable CostAverage Total CostMarginal cost1003601602000.33000.834001.3050046060037001.680022402. If the market price is Rs 3,what will be the profit/ loss of the firm?
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
QUESTION FOUR (20 Marks) 4.1 Complete Table 4.1 given below showing quantity, fixed cost, variable cost,...
QUESTION FOUR 4.1 Complete Table 4.1 given below showing quantity, fixed cost, variable cost, total cost and marginal cost. Quantity Fixed Cost (R) Variable Cost (R) Total Cost (R) Marginal Cost (R) 0 25 0 (a) (d) 2 (b) 18 (c) (g) 4 (e) 31 (f) (j) 6 (h) (41) (i) 4.2 Using examples distinguish between fixed costs and variable costs. 4.3 Differentiate between marginal cost and marginal revenue. 4.4 Compare and contrast accounting and economic profits.
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Complete the table below showing labor (ex: # of workers), total output, and the marginal product...
Complete the table below showing labor (ex: # of workers), total output, and the marginal product (MP) of labor for a company. Labor Total Output MP of labor 0 0 NA 1 5 5 2 12 3 6 4 4 5 25 6 27 2
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT