Question

In: Operations Management

The following table lists the components needed to assemble an end item, lead times (in weeks),...

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.) The latest week

Solutions

Expert Solution

Answer: Let's present the given data in a tabular and diagrammatical form as mentioned below:

(Note: We simply have shown the table in a verticle form to get the above diagram)

Which means, Each unit of L requires 2 Units of B and 3 Units of J,

Each unit of C requires 2 units of each item G and item B

Each unit of K requires 4 units of H and 2 units of B, and

End Item requires 2 units of L, 1 unit of C, and 3 units of K

Answer a) Here, 43 units of the end item to be produced. We will find the required additional units by applying the following formula:

Additional Units of Item B =

Calculate the following table as mentioned below:

Where Col6 = [(Col2 X Col3) - Col4] X Col5,

Total units of B required for 43 units = Sum of Col3

Hence, Additional units required for Item B = Total Units of B required for 43 end items - Amount on hand of item B = 442 - 32 = 410 Units

Answer b) Here, first the total lead time for each of the path mentioned in the above diagram:

Here we note that the longest lead time is 8 weeks.

Hence, The latest week in which the order can be started The latest week in which the order can be started and still be ready on the ship on time =

= Scheduled start of the week - the longest lead time

Where scheduled start of week = 13 (as given in the question)

The latest week in which the order can be started and still be ready on the ship on time= 13 - 8 = 5 Week


Related Solutions

The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 16 G(2), B(2) K 4 21 H(4), B(2) B 3 26 J 4 33 G 4 4 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 14 G(2), B(2) K 3 20 H(4), B(2) B 2 31 J 3 28 G 3 4 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 2 2 2 2 2 2 Amount on hand 0 8 11 23 9 28 6 0 a. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 1 3 4 4 2 1 2 1 Amount on hand 0 10 9 25 11 29 6 0 End Item B(2)   C D(3) E(2) / F(3) G(2) / E(2) H(4) / E(2) a. If 20 units of the end item are to be assembled, how many additional units of E...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine...