Question

In: Operations Management

The following table lists the components needed to assemble an end item, lead times (in weeks),...

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.) The latest week

Solutions

Expert Solution

a)

Net Requirement of End Item = Gross Requirement - On Hand Inventory = 43-0 = 43 units

Net Requirement of L = Net Requirement of End Item*2 - On Hand Inventory

Net Requirement of L = 43*2 - 11 = 75 units

Net Requirement of C = Net Requirement of End Item*1 - On Hand Inventory

Net Requirement of C = 43*1 - 17 = 26 units

Net Requirement of K = Net Requirement of End Item*3 - On Hand Inventory

Net Requirement of K = 43*3 - 23 = 106

Net Requirement of B = Net Requirement of L*2 + Net Requirement of C*2 + Net Requirement of K*2 - 34

Net Requirement of B = 75*2 + 26*2 + 106*2 - 34

Net Requirement of B = 380

b)

End Item to be shipped in Week 11. Assembly to be started in Week 10 (Lead Time 1 Week)

L,C & K should be ready by Week 10.

Assembly of L should be started in Week 8 (Lead Time 2 Week)

Assembly of C should be started in Week 7 (Lead Time 3 Week)

Assembly of K should be started in Week 6 (Lead Time 4 Week)

B should be ready by Week 3 (Lead Time 3 weeks (it is part of K which should be ready by Week 6))

J Should be ready by Week 5. (Lead Time 3 weeks)

G should be ready by Week 4. (Lead Time 3 weeks)

H should be ready by Week 3. (Lead Time 3 weeks)

From above, Latest Week = Week 3


Related Solutions

Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Fill in the table below so that it lists every reagent needed for a PCR reaction...
Fill in the table below so that it lists every reagent needed for a PCR reaction and give its purpose in the reaction. You may or may not need all the rows in this table. Reagent Purpose 5X Taq Buffer F and R primers Supplies co-factor for polymerase Building blocks for new DNA Water
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for...
The accompanying table lists a random selection of usual travel times to​ school, in​ minutes, for 40 secondary school students in country A. A second selection of usual travel times to​ school, in​ minutes, was randomly selected for 40 students in country B. Complete parts​ a) and​ b). Sample Country A   Sample Country B 45   29 5   10 4   9 14   30 50   5 21   8 21   7 19   15 21   10 21   36 24   16 36   10 14   24...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he...
A statisitcs instructor participates in triathalons. the table lists the times in minutes and seconds, he recorded while riding five laps through each mile of a 3-mile loop. Use a .05 significance level to test the claim that is takes the same time to ride each of the miles. Mile 1 3:15 3:25 3:23 3:22 3:22 Mile 2 3:19 3:23 3:20 3:17 3:19 Mile 3 3:34 3:30 3:29 3:30 3:29 Determine the null and alternate hypotheses. Find the F statistic...
The following table lists the month-end prices from May 2017 to July 2018 of the Spider...
The following table lists the month-end prices from May 2017 to July 2018 of the Spider S&P 500 Index ETF (SPY) and iShares 20+ Treasury Bond ETF (TLT), respectively. During this time period the average annual yield for the one-month Treasury bills is 1.292% or 0.1077% per month. Apply the following equation to calculate the monthly returns from June 2017 to July 2018 for SPY and TLT, respectively. The monthly return for month n: rn = (Current month-end price –...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded...
A certain statistics instructor participates in triathlons. The accompanying table lists times​ (in seconds) he recorded while riding a bicycle. He recorded every time he rode and randomly picked five laps through each mile of a​ 3-mile loop. Use a .05 significance level to test the claim that it takes the same time to ride each of the miles. Mile 1 194 205 203 202 201 Mile 2 198 201 200 196 200 Mile 3 215 211 209 212 209...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT