Question

In: Advanced Math

13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...

13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project.

Table EX 13.7

Activity

Predecessor

Duration (Weeks)

A

6

B

2

C

A

4

D

B

5

E

B

2

F

C, D

4

G

C, D

7

H

E, G

5

I

F

4

  1. Construct an activity on node network for the project.
  2. Identify the paths and path project durations.
  3. Determine the critical path and the expected project completion time.
  4. Find the ES, LS, EF, LF, and slack time for each activity.

Solutions

Expert Solution

Construct an activity on node network for the project.

Identify the paths and path project durations.

Path Duration(Weeks)
A-C-G-H 6+4+7+5 = 22
A-C-F-I 6+4+4+4 = 18
B-D-F-I 2+5+4+4 = 15
B-E-H 2+2+5 = 9
B-D-G-H 2+5+7+5 = 19

Determine the critical path and the expected project completion time.

Critical path is the longest path and here the critical path is A-C-G-H with duration 22 weeks

Expected project completion time is duration of critical path = 22 weeks

Find the ES, LS, EF, LF, and slack time for each activity.

ES LS EF LF Slack
A 0 0 6 6 0
B 0 3 2 5 3
C 6 6 10 10 0
D 2 5 7 10 3
E 2 15 4 17 13
F 10 14 14 18 4
G 10 10 17 17 0
H 17 17 22 22 0
I 14 18 18 22 4

Forward Pass

Early Start of A = 0

Early Finish of A = Early Start of A + Duration of A = 0+6 = 6

Early Start of C = Early Finish of A = 6

Early Finish of C = Early Start of C + Duration of C = 6+4 = 10

Early Start of G = Early Finish of C = 10

Early Finish of G = Early Start of G + Duration of G = 10+7 = 17

Early Start of F = Early Finish of C = 10

Early Finish of F = Early Start of F + Duration of F = 10+4 = 14


Early Start of B = 0

Early Finish of B = Early Start of B + Duration of B = 0+2 = 2

Early Start of D = Early Finish of B = 2

Early Finish of D = Early Start of D + Duration of D = 2+5 = 7

Early Start of E = Early Finish of B = 2

Early Finish of E = Early Start of E + Duration of E = 2+2 = 4

Early Start of H = Max(Early Finish of E, Early Finish of G) = Max(4,17) = 17

Early Finish of H = Early Start of H + Duration of H = 17+5 = 22

Early Start of I = Early Finish of F = 14

Early Finish of I = Early Start of I + Duration of I = 14+4 = 18

Backward pass

Late Finish of H = 22

Late Start of H = Late Finish of H - Duration of H = 22-5 = 17


Late Finish of I = 22

Late Start of I = Late Finish of I - Duration of I = 22-4 = 18


Late Finish of G = Late Start of H = 17

Late Start of G = Late Finish of G - Duration of G = 17-7 = 10


Late Finish of C = Late Start of G = 10

Late Start of C = Late Finish of C - Duration of C = 10-4 = 6


Late Finish of D = Late Start of G = 10

Late Start of D = Late Finish of D - Duration of D = 10-5 = 5


Late Finish of F = Late Start of I = 18

Late Start of F = Late Finish of F - Duration of F = 18-4 = 14

Late Finish of E = Late Start of H = 17

Late Start of E = Late Finish of E - Duration of E = 17-2 = 15


Late Finish of A = late start of C = 6

late Start of A = Late finish of A - Duration of A = 6-6 = 0


Late Finish of B = Min (Late start of D , and Late start of E) = Min(5,15) = 5

Late Start of B = Late Finish of B - Duration of B = 5-2 = 3

Slack = Late Start - Early Start = Late Finish - Early Finish


Related Solutions

A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
The table below defines number of working activities needed to accomplish a House project. The relationships...
The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type. Dependency Duration in days I.D Activity name ................................ 20 A Excavation work A 5 B Plain concrete work A 6 C Reinforced concrete work B & C 2 D Install grass C 10 E Build walls E 8 F Build roof E 7 G Plaster work F & G...
A project for improving a billing process has the following precedence relationships and activity​ times: Using...
A project for improving a billing process has the following precedence relationships and activity​ times: Using the info below calculate the slack for each activity. Which activities are on the critical path?                                                                                                           Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 5 ---- B 10 ----- C 6 A D 14 ​B, C E 9 B F 5 D G 3 E H 6 ​F, G
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The following table lists the activities needed to complete a project. The first column lists the...
The following table lists the activities needed to complete a project. The first column lists the activities and the “follows” column shows which other activity or activities, (if any), must be completed before these activities can start. The remaining columns give three estimates of the activity duration; the mean duration calculated from these estimates and standard deviation assuming a beta distribution of activity duration. Activity Follows Estimates of durations (days) Optimistic Most likely Pessimistic A -- 3 6 15 B...
The DuPont equation shows the relationships among asset management, debt management
The DuPont equation shows the relationships among asset management, debt management, and-(Select-liquidity,market,profitability) of Item 1 ratios. Management can use the DuPont equation to analyze ways of improving the firm's performance. Its equation is:Ratio analysis is important to understand and interpret financial statements; however, sound financial analysis involves more than just calculating and interpreting numbers.(-Select one-Quantitative,Qualitative,Foreign) of Item 1 factors also need to be considered.Quantitative Problem: Rosnan Industries' 2019 and 2018 balance sheets and income statements are shown below.Balance Sheets:20192018Cash and...
Draw the phylogenetic tree that shows that understanding of the evolutionary relationships of all invertebrates among...
Draw the phylogenetic tree that shows that understanding of the evolutionary relationships of all invertebrates among the major phyla of metazoans. What are the major clades shown on the tree? Why are the phyla grouped together in the specific clades that you have drawn? What are the synapomorphies that define each of the clades and the different phyla within them? What sources of evidence were used to reconstruct the phylogeny that you have drawn? Are certain sources of evidence more...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
What are the important relationships among Caterpillar’s value-chain activities? What are the important interdependencies? For each...
What are the important relationships among Caterpillar’s value-chain activities? What are the important interdependencies? For each activity, identify the relationships and interdependencies. Inbound Logistics Operations Outbound Logistics Marketing and Sales Service Procurement Technology Development Human Resource Management General Admin Inbound Logistics Operations Outbound Logistics Marketing and Sales Service Procurement Technology Development Human Resource Management General Admin
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT