13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project.
Table EX 13.7
Activity |
Predecessor |
Duration (Weeks) |
A |
– |
6 |
B |
– |
2 |
C |
A |
4 |
D |
B |
5 |
E |
B |
2 |
F |
C, D |
4 |
G |
C, D |
7 |
H |
E, G |
5 |
I |
F |
4 |
Construct an activity on node network for the project.
Identify the paths and path project durations.
Path | Duration(Weeks) |
A-C-G-H | 6+4+7+5 = 22 |
A-C-F-I | 6+4+4+4 = 18 |
B-D-F-I | 2+5+4+4 = 15 |
B-E-H | 2+2+5 = 9 |
B-D-G-H | 2+5+7+5 = 19 |
Determine the critical path and the expected project completion time.
Critical path is the longest path and here the critical path is A-C-G-H with duration 22 weeks
Expected project completion time is duration of critical path = 22 weeks
Find the ES, LS, EF, LF, and slack time for each activity.
ES | LS | EF | LF | Slack | |
A | 0 | 0 | 6 | 6 | 0 |
B | 0 | 3 | 2 | 5 | 3 |
C | 6 | 6 | 10 | 10 | 0 |
D | 2 | 5 | 7 | 10 | 3 |
E | 2 | 15 | 4 | 17 | 13 |
F | 10 | 14 | 14 | 18 | 4 |
G | 10 | 10 | 17 | 17 | 0 |
H | 17 | 17 | 22 | 22 | 0 |
I | 14 | 18 | 18 | 22 | 4 |
Forward Pass
Early Start of A = 0
Early Finish of A = Early Start of A + Duration of A = 0+6 = 6
Early Start of C = Early Finish of A = 6
Early Finish of C = Early Start of C + Duration of C = 6+4 = 10
Early Start of G = Early Finish of C = 10
Early Finish of G = Early Start of G + Duration of G = 10+7 = 17
Early Start of F = Early Finish of C = 10
Early Finish of F = Early Start of F + Duration of F = 10+4 = 14
Early Start of B = 0
Early Finish of B = Early Start of B + Duration of B = 0+2 = 2
Early Start of D = Early Finish of B = 2
Early Finish of D = Early Start of D + Duration of D = 2+5 = 7
Early Start of E = Early Finish of B = 2
Early Finish of E = Early Start of E + Duration of E = 2+2 = 4
Early Start of H = Max(Early Finish of E, Early Finish of G) = Max(4,17) = 17
Early Finish of H = Early Start of H + Duration of H = 17+5 = 22
Early Start of I = Early Finish of F = 14
Early Finish of I = Early Start of I + Duration of I = 14+4 = 18
Backward pass
Late Finish of H = 22
Late Start of H = Late Finish of H - Duration of H = 22-5 = 17
Late Finish of I = 22
Late Start of I = Late Finish of I - Duration of I = 22-4 = 18
Late Finish of G = Late Start of H = 17
Late Start of G = Late Finish of G - Duration of G = 17-7 = 10
Late Finish of C = Late Start of G = 10
Late Start of C = Late Finish of C - Duration of C = 10-4 = 6
Late Finish of D = Late Start of G = 10
Late Start of D = Late Finish of D - Duration of D = 10-5 = 5
Late Finish of F = Late Start of I = 18
Late Start of F = Late Finish of F - Duration of F = 18-4 = 14
Late Finish of E = Late Start of H = 17
Late Start of E = Late Finish of E - Duration of E = 17-2 = 15
Late Finish of A = late start of C = 6
late Start of A = Late finish of A - Duration of A = 6-6 = 0
Late Finish of B = Min (Late start of D , and Late start of E) =
Min(5,15) = 5
Late Start of B = Late Finish of B - Duration of B = 5-2 = 3
Slack = Late Start - Early Start = Late Finish - Early Finish