Question

In: Operations Management

A project involves the following activities, their predecessors, and the times (in weeks) associated with each...

A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity.

Activity

Immediate Predecessor

Optimistic (a)

Most Likely (m)

Pessimistic (b)

A

--

1

2

3

B

--

2

3

4

C

--

3

4

5

D

A

4

5

12

E

B

1

3

5

F

B

3

4

11

G

C

5

6

13

H

D, E

8

9

10

I

F, G

4

5

6

J

H, I

1

1

1

What is the probability that the project will be finished in 21 weeks or less?

What is the probability that the project will take between 19 to 21 weeks to be completed?

If we want a 95% chance of completing the project on time, how far ahead of the schedule meeting time should the project be started?

If activity F is delayed and takes 10 weeks to complete, would the project completion time be any different? If yes, what would be the critical path and the expected completion time?

Solutions

Expert Solution

EXPECTED TIME

FORMULA:

(a + (4m) + b) / 6

A = (1 + (4 * 2) + 3) / 6 = 2

B = (2 + (4 * 3) + 4) / 6 = 3

C = (3 + (4 * 4) + 5) / 6 = 4

D = (4 + (4 * 5) + 12) / 6 = 6

E = (1 + (4 * 3) + 5) / 6 = 3

F = (3 + (4 * 4) + 11) / 6 = 5

G = (5 + (4 * 6) + 13) / 6 = 7

H = (8 + (4 * 9) + 10) / 6 = 9

I = (4 + (4 * 5) + 6) / 6 = 5

J = (1 + (4 * 1) + 1) / 6 = 1

VARIANCE

FORMULA:

((b - a) / 6) ^ 2

A = (3 - 1) / 6) ^ 2 = 0.11

B = (4 - 2) / 6) ^ 2 = 0.11

C = (5 - 3) / 6) ^ 2 = 0.11

D = (12 - 4) / 6) ^ 2 = 1.78

E = (5 - 1) / 6) ^ 2 = 0.44

F = (11 - 3) / 6) ^ 2 = 1.78

G = (13 - 5) / 6) ^ 2 = 1.78

H = (10 - 8) / 6) ^ 2 = 0.11

I = (6 - 4) / 6) ^ 2 = 0.11

J = (1 - 1) / 6) ^ 2 = 0

CPM ANALYSIS


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

2

0

2

0

2

0

B

3

0

3

2

5

2

C

4

0

4

1

5

1

D

6

2

8

2

8

0

E

3

3

6

5

8

2

F

5

3

8

7

12

4

G

7

4

11

5

12

1

H

9

8

17

8

17

0

I

5

11

16

12

17

1

J

1

17

18

17

18

0

FORWARD PASS

1. Go from left to right in a network.

2. ES = maximum of the EF value from all the direct predecessors.

3. EF = ES + Duration.

BACKWARD PASS

1. Go from right to left in a network.

2. LF = minimum of the LS value from all the direct predecessors.

3. LS = LF - Duration.

CRITICAL PATH

1. Total slack of all activities should be 0.

2. The total duration of all the activities should be the highest.

3. Slack = LF - EF or LS - ES

CRITICAL PATH & DURATION

A + D + H + J = 18

ESTIMATES

VARIANCE OF CRITICAL PATH = 0.11 + 1.78 + 0.11 + 0 = 2

Due time = 21

Expected time = 18

Variance = 2

Stdev = sqrt(variance) = sqrt(2) = 1.41(ROUNDED)

Z = DUE - EXPECTED / STDEV

Z = 21 - 18 / 1.41 = 2.13

Z value of 2.13 gives a distribution of 0.9834 OR 98.34 % probability of completion of the project by the due time of 21





Related Solutions

A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
Organizing a project involves which of the following activities? Multiple Choice Defining the project Controlling the...
Organizing a project involves which of the following activities? Multiple Choice Defining the project Controlling the project All of these are correct Planning the project
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT