Question

In: Operations Management

A project involves the following activities, their predecessors, and the times (in weeks) associated with each...

A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity.

Activity

Immediate Predecessor

Optimistic (a)

Most Likely (m)

Pessimistic (b)

A

--

1

2

3

B

--

2

3

4

C

--

3

4

5

D

A

4

5

12

E

B

1

3

5

F

B

3

4

11

G

C

5

6

13

H

D, E

8

9

10

I

F, G

4

5

6

J

H, I

1

1

1

What is the probability that the project will be finished in 21 weeks or less?

What is the probability that the project will take between 19 to 21 weeks to be completed?

If we want a 95% chance of completing the project on time, how far ahead of the schedule meeting time should the project be started?

If activity F is delayed and takes 10 weeks to complete, would the project completion time be any different? If yes, what would be the critical path and the expected completion time?

Solutions

Expert Solution

EXPECTED TIME

FORMULA:

(a + (4m) + b) / 6

A = (1 + (4 * 2) + 3) / 6 = 2

B = (2 + (4 * 3) + 4) / 6 = 3

C = (3 + (4 * 4) + 5) / 6 = 4

D = (4 + (4 * 5) + 12) / 6 = 6

E = (1 + (4 * 3) + 5) / 6 = 3

F = (3 + (4 * 4) + 11) / 6 = 5

G = (5 + (4 * 6) + 13) / 6 = 7

H = (8 + (4 * 9) + 10) / 6 = 9

I = (4 + (4 * 5) + 6) / 6 = 5

J = (1 + (4 * 1) + 1) / 6 = 1

VARIANCE

FORMULA:

((b - a) / 6) ^ 2

A = (3 - 1) / 6) ^ 2 = 0.11

B = (4 - 2) / 6) ^ 2 = 0.11

C = (5 - 3) / 6) ^ 2 = 0.11

D = (12 - 4) / 6) ^ 2 = 1.78

E = (5 - 1) / 6) ^ 2 = 0.44

F = (11 - 3) / 6) ^ 2 = 1.78

G = (13 - 5) / 6) ^ 2 = 1.78

H = (10 - 8) / 6) ^ 2 = 0.11

I = (6 - 4) / 6) ^ 2 = 0.11

J = (1 - 1) / 6) ^ 2 = 0

CPM ANALYSIS


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

2

0

2

0

2

0

B

3

0

3

2

5

2

C

4

0

4

1

5

1

D

6

2

8

2

8

0

E

3

3

6

5

8

2

F

5

3

8

7

12

4

G

7

4

11

5

12

1

H

9

8

17

8

17

0

I

5

11

16

12

17

1

J

1

17

18

17

18

0

FORWARD PASS

1. Go from left to right in a network.

2. ES = maximum of the EF value from all the direct predecessors.

3. EF = ES + Duration.

BACKWARD PASS

1. Go from right to left in a network.

2. LF = minimum of the LS value from all the direct predecessors.

3. LS = LF - Duration.

CRITICAL PATH

1. Total slack of all activities should be 0.

2. The total duration of all the activities should be the highest.

3. Slack = LF - EF or LS - ES

CRITICAL PATH & DURATION

A + D + H + J = 18

ESTIMATES

VARIANCE OF CRITICAL PATH = 0.11 + 1.78 + 0.11 + 0 = 2

Due time = 21

Expected time = 18

Variance = 2

Stdev = sqrt(variance) = sqrt(2) = 1.41(ROUNDED)

Z = DUE - EXPECTED / STDEV

Z = 21 - 18 / 1.41 = 2.13

Z value of 2.13 gives a distribution of 0.9834 OR 98.34 % probability of completion of the project by the due time of 21





Related Solutions

A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
The estimated times and immediate predecessors for activities in a project are given below in the...
The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent. Task                           Predecessor                Optimistic   Most Likely   Pessemistic                                                                             Time (wks)    time (wks)     time (wks) Architectural design                            --         10                  30                    45 Software                      Architectural design    13                  15                    23 Compilg                      Software                          2                  3                    4 Hardware                    Architectural design    15                  20                    25 Integration                   Software & Hardware   20                  22                    24 Bug fixes                     Integration                   3                    4                      11             a) Draw an activity-on-node...
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 1 3 5 C A 2 5 11 D A 1 8 9 E B 1 2 3 F C,D 1 6 11 G D,E 1 2 3 H F,G 2 3 3 b. What is the critical path? B-E-G-H A-C-F-H A-D-F-H A-D-G-H c. What is the expected project completion time? (Round your answer...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT