Question

In: Operations Management

The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.


The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. 

image.png

a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? 

b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? 

c) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.

Solutions

Expert Solution

ACTIVITY

EXPECTED TIME

VARIANCE

A

(9 + (4 * 10) + 11) / 6 = 10

((11 - 9) / 6)^2 = 0.111

B

(4 + (4 * 10) + 16) / 6 = 10

((16 - 4) / 6)^2 = 4

C

(9 + (4 * 10) + 11) / 6 = 10

((11 - 9) / 6)^2 = 0.111

D

(5 + (4 * 8) + 11) / 6 = 8

((11 - 5) / 6)^2 = 1

EXPECTED TIME = (OPTIMISTIC TIME + (4 * MOST LIKELY TIME) + PESSIMISTIC TIME) / 6

VARIANCE = ((PESSIMISTIC TIME - OPTIMISTIC TIME) / 6)^2


CPM ANALYSIS FOR EXPECTED PROJECT DURATION


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

10

0

10

0

10

0

B

10

0

10

2

12

2

C

10

10

20

10

20

0

D

8

10

18

12

20

2


FORWARD PASS: ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT. EF = ES + DURATION OF THE ACTIVITY.

BACKWARD PASS: LF = MINIMUM LS OF ALL SUCCESSOR ACTIVITIES; COMPLETION TIME OF THE PROJECT IF NO SUCCESSORS ARE PRESENT. LS = LF - DURATION OF THE ACTIVITY.

SLACK = LF - EF, OR, LS - ES

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

1. CRITICAL PATH = AC

DURATION OF PROJECT = 20

NON CRITICAL PATH = BD = 10 + 8 = 18

2. VARIANCE OF CRITICAL PATH = 0.111 + 0.111 = 0.222

VARIANCE OF NON CRITICAL PATH = 4 + 1 = 5



3. Because the variance of the noncritical path is 5, we can say that the higher variability of the noncritical path can cause the noncritical path to take more time than the critical path and therefore, we might have BD acting as the critical path.


Related Solutions

19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT