Question

In: Statistics and Probability

A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...

A project has the following activities, precedence relationships, and time estimates in weeks:

Activity

Immediate Predecessor

Activities

Optimistic

Time (to)

Most Likely Time (tm)

Pessimistic

Time (tp)

A

15

20

25

B

8

10

12

C

A

25

30

40

D

B

15

15

15

E

B

22

25

27

F

E

15

20

22

G

D

20

20

22

a.   Compute the expected time and variance for each activity.

b.   Determine the critical path and the expected duration of the project.

c.   What is the probability that the project will take longer than 56 weeks to complete?

Solutions

Expert Solution


Related Solutions

A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project for improving a billing process has the following precedence relationships and activity​ times: Using...
A project for improving a billing process has the following precedence relationships and activity​ times: Using the info below calculate the slack for each activity. Which activities are on the critical path?                                                                                                           Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 5 ---- B 10 ----- C 6 A D 14 ​B, C E 9 B F 5 D G 3 E H 6 ​F, G
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence relationships (be sure to use the triple time estimate). All times are in days: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 6 --- B 5 7 10 --- C 2 3 11 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table...
13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path project durations. Determine the critical path and the expected project completion time. Find the...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT