Question

In: Operations Management

Organizing a project involves which of the following activities? Multiple Choice Defining the project Controlling the...

Organizing a project involves which of the following activities?

Multiple Choice

  • Defining the project

  • Controlling the project

  • All of these are correct

  • Planning the project

Solutions

Expert Solution

The correct answer is All of these are Correct.

Organizing a project involves all the activities listed here:

  1. Defining the project
  2. Planning the project
  3. Controlling the project

Defining the project is basically writing a complete project description involving Project Overview, Purpose and Need, Background, Previous Work and Expected Outcome.

Planning the project is planning the implementation along with the timeline. It involves Implementation Method, Timeline, Benefits and Costs and the Impact.

Controlling the Project is the actual implementation of the project. The project manager needs to organize the project resources to make sure each aspect of the project is under control and is happening according to the proposed timeline.


Related Solutions

2. Which of the following best describes the nature of personal selling? Multiple Choice It involves...
2. Which of the following best describes the nature of personal selling? Multiple Choice It involves direct spoken communication between sellers and potential customers. It costs less than advertising for reaching a large, widespread market. It tries to communicate with many customers at the same time. It refers to "promoting" at trade shows, demonstrations, and contests. It is less flexible than mass selling 3. .Agent wholesalers are Multiple Choice mainly concerned with buying and selling. used by small companies that...
Discuss and elaborate On each  benefits of budgeting in regard to banks *Defining objectives *Planning *Organizing *Controlling...
Discuss and elaborate On each  benefits of budgeting in regard to banks *Defining objectives *Planning *Organizing *Controlling *Co- ordinating *Communicating *Motivating
What are some of the Organizing Activities within a Project?
What are some of the Organizing Activities within a Project?
Organizing the project involves securing a. adequate funds for the project. b. a contract with the...
Organizing the project involves securing a. adequate funds for the project. b. a contract with the customer. c. a project management information system. d. the appropriate resources to perform the work.
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
1. What is a defining characteristic of a free trade area? Multiple Choice Factors of production...
1. What is a defining characteristic of a free trade area? Multiple Choice Factors of production are allowed to move freely between member nations. Each member country is allowed to determine its own trade policies with regard to nonmembers. Member nations are required to have a common currency. Member nations are required to have a common monetary and fiscal policy. Member nations are required to have a central political apparatus that coordinates economic, social, and foreign policy. 2. Establishment of...
Which of the following is not true of symmetric encryption? A It often involves multiple iterations...
Which of the following is not true of symmetric encryption? A It often involves multiple iterations encryption B It can be decrypted using a key C Breach of the encryption key can enable a brute force attack to be successful D Encryption Key must be protected to ensure password security. Which of the following best describes the use of security roles? A A group of users who have been granted the same level of access to the same objects within...
Given multiple tools and techniques for analyzing and controlling the flow of supply chain activities- process...
Given multiple tools and techniques for analyzing and controlling the flow of supply chain activities- process mapping, process analysis, and customer relationship management (CRM)- recommend how to improve supply chain effectiveness whil increasing customer repsonse time and service levels. Develop a process flowchart and detemine how effective the supply chain process is in achieving designed goals. Detemine how to change a process to improve supply chain effectiveness and efficiency by revising and war designing a new replacement process Explain how...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT