In: Operations Management
Given a simple project illustrated in the following table
Activity | Immediate Predecessors | Time (weeks) |
1 | - | 2 |
2 | - | 3 |
3 | 1, 2 | 2 |
4 | 3 | 5 |
5 | 3 | 4 |
The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
CRITICAL |
1 |
3 |
0 |
3 |
0 |
3 |
0 |
YES |
2 |
2 |
0 |
2 |
0 |
3 |
1 |
|
3 |
2 |
3 |
5 |
3 |
5 |
0 |
YES |
4 |
5 |
5 |
10 |
5 |
10 |
0 |
YES |
5 |
4 |
5 |
9 |
6 |
10 |
1 |
FORWARD PASS
We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.
BACKWARD PASS
We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.
SLACK
Slack is the value which is determined by subtracting EF from the LF or ES from the LS.
CRITICAL PATH
Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.
CRITICAL PATH = 1-3-4
DURATION OF PROJECT = 10
LF OF 4 = 10
Do leave a like for the answer if you found it helpful.