Question

In: Operations Management

Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...

Given a simple project illustrated in the following table

Activity Immediate Predecessors Time (weeks)
1 - 2
2 - 3
3 1, 2 2
4 3 5
5 3 4

The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?

Solutions

Expert Solution


ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

CRITICAL

1

3

0

3

0

3

0

YES

2

2

0

2

0

3

1

3

2

3

5

3

5

0

YES

4

5

5

10

5

10

0

YES

5

4

5

9

6

10

1

FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH = 1-3-4

DURATION OF PROJECT = 10

LF OF 4 = 10

Do leave a like for the answer if you found it helpful.


Related Solutions

A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
The estimated times and immediate predecessors for activities in a project are given below in the...
The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent. Task                           Predecessor                Optimistic   Most Likely   Pessemistic                                                                             Time (wks)    time (wks)     time (wks) Architectural design                            --         10                  30                    45 Software                      Architectural design    13                  15                    23 Compilg                      Software                          2                  3                    4 Hardware                    Architectural design    15                  20                    25 Integration                   Software & Hardware   20                  22                    24 Bug fixes                     Integration                   3                    4                      11             a) Draw an activity-on-node...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT