Question

In: Operations Management

19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...

19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below:

Activity Immediate Predecessor Activity time (in days)
A None 3
B A 2
C A 1
D B, C 3
E D 4



In CPM, what is the completion time of the project?

A

12 days

B

11 days

C

13 days

20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation (MAD)?

Actual

Forecast

Forecast Error

10

11

-1

8

10

-2

10

8

2

6

6

0

9

8

1

A

-1.0

B

-0.2

C

1.2

D

0.0

21. Which of the following statements is INCORRECT regarding corporate missions?

A

They reflect a company's purpose.

B

They indicate what a company intends to contribute to society.

C

They are the long-term action plans to be adopted by companies.

D

They define a company's reason for existence.

Solutions

Expert Solution

21. The correct answer is option C.

Mission of an organization describes the function of organization and what exactly the organization is trying to achieve. Mission is considered as the path which helps in meeting the goal. Drafting a companywide mission statement is important for the organization because it helps the company to make strategic plans to meet the goals. Mission statement should be formulated keeping in mind the following business aspects. They are: -

  • The goal of the organization and the underlying philosophies.
  • Who the company is because mission statement gives clear picture about the customers, employees, suppliers, competitors, etc.
  • It should be formulated keeping in mind the business processes and activities and what is exactly done by the business.
  • It also involves the value the business is bringing to the customers, stakeholders, community, etc. and what is the reason behind this.

Related Solutions

The estimated times and immediate predecessors for activities in a project are given below in the...
The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent. Task                           Predecessor                Optimistic   Most Likely   Pessemistic                                                                             Time (wks)    time (wks)     time (wks) Architectural design                            --         10                  30                    45 Software                      Architectural design    13                  15                    23 Compilg                      Software                          2                  3                    4 Hardware                    Architectural design    15                  20                    25 Integration                   Software & Hardware   20                  22                    24 Bug fixes                     Integration                   3                    4                      11             a) Draw an activity-on-node...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT