Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...

Activities, predecessors and duration for a School Building Project

Activity

Description

Immediate predecessor

Duration (days)

A

Clear Site and mobilize labour and equipment

None

5

B

Excavate foundation

A

15

C

Procure materials (sand, cement, chippings etc.)

A

10

D

Pour foundation concrete

B, C

5

E

Mould sandcrete blocks (substructure)

C

5

F

Construct substructure block work

D, E

15

G

Construct superstructure block work

F, H

30

H

Make doors and window frames

I

10

I

Procure and preserve roof timber

C

10

J

Roofing, plastering and painting

G, I

25

K

Fabricate roof trusses

I

15

L

Mould sandcrete blocks (superstructure)

C

10

  1. Draw the network diagram.
  2. What is the critical path of the above project?
  3. Calculate the total and free floats for the activities.

Solutions

Expert Solution

For each non-critical activity, the total float, and free float calculations are shown in Table

Activity Earliest time Latest time Earliest time Latest time
(i,j) Duration Start Finish Finish Start Total Float Free Float
(tij) (Ei) (Ej) (Li) (Lj) (Ei+tij) (Lj-tij) (Lj-tij)-Ei (Ej-Ei)-tij
[1] [2] [3] [4] [5] [6] (7)=(3)+(2) (8)=(6)-(2) (9)=(8)-(3) (10)=((4)-(3))-(2)
2-4 10 5 15 5 20 15 10 5 0
4-3 0 15 20 20 20 15 20 5 5
4-5 5 15 25 20 25 20 20 5 5
4-6 10 15 25 20 30 25 20 5 0
4-9 10 15 95 20 95 25 85 70 70
6-7 10 25 40 30 40 35 30 5 5
6-8 0 25 70 30 70 25 70 45 45
6-9 15 25 95 30 95 40 80 55 55

note that for critical activity all floats are 0.

critical path is shown in fig. activities along the critical path are the critical activites'

thank you


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...