Question

In: Civil Engineering

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...

Activities, predecessors and duration for a School Building Project

Activity

Description

Immediate predecessor

Duration (days)

A

Clear Site and mobilize labour and equipment

None

5

B

Excavate foundation

A

15

C

Procure materials (sand, cement, chippings etc.)

A

10

D

Pour foundation concrete

B, C

5

E

Mould sandcrete blocks (substructure)

C

5

F

Construct substructure block work

D, E

15

G

Construct superstructure block work

F, H

30

H

Make doors and window frames

I

10

I

Procure and preserve roof timber

C

10

J

Roofing, plastering and painting

G, I

25

K

Fabricate roof trusses

I

15

L

Mould sandcrete blocks (superstructure)

C

10

  1. Draw the network diagram.
  2. What is the critical path of the above project?
  3. Calculate the total and free floats for the activities.

Solutions

Expert Solution

For each non-critical activity, the total float, and free float calculations are shown in Table

Activity Earliest time Latest time Earliest time Latest time
(i,j) Duration Start Finish Finish Start Total Float Free Float
(tij) (Ei) (Ej) (Li) (Lj) (Ei+tij) (Lj-tij) (Lj-tij)-Ei (Ej-Ei)-tij
[1] [2] [3] [4] [5] [6] (7)=(3)+(2) (8)=(6)-(2) (9)=(8)-(3) (10)=((4)-(3))-(2)
2-4 10 5 15 5 20 15 10 5 0
4-3 0 15 20 20 20 15 20 5 5
4-5 5 15 25 20 25 20 20 5 5
4-6 10 15 25 20 30 25 20 5 0
4-9 10 15 95 20 95 25 85 70 70
6-7 10 25 40 30 40 35 30 5 5
6-8 0 25 70 30 70 25 70 45 45
6-9 15 25 95 30 95 40 80 55 55

note that for critical activity all floats are 0.

critical path is shown in fig. activities along the critical path are the critical activites'

thank you


Related Solutions

QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT