Question

In: Advanced Math

The following table represents a project with four activities. All times are in weeks. Activity Immediate...

The following table represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic Time

Most Likely Time

Pessimistic Time

A

-

4

8

16

B

-

7

8

9

C

A

6

10

18

D

B

5

13

18

A. According to the data in the table. What is the critical path?

B. According to the data in the table, what is the minimum expected completion time for the project?

C. According to the table there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. If you wished to find the probability of finishing the project in 21 weeks or fewer. It would be necessary to find the variance and then the standard deviation to be used with the normal distribution. What variance and standard deviation would be used?

D. According to the table, There are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 20 weeks or fewer.

Solutions

Expert Solution


Related Solutions

A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 6 2 1 3 3 15 3 1 3 4 11 4 1 1 2 9 5 2 2 6 7 6 3 3 7 8 7 4 4 6 8 8 5,6 2 3 4 9 8 1 4 7 10 7 3 4 5 11 9,10 5 6 7    b. Indicate the critical path. 1-2-5-8-9-11...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT