Question

In: Operations Management

For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL...

For the given data, crash the project completely.

ACTIVITY

PREDECESSOR

NORMAL TIME(DAYS)

MAX CRASH TIME

NORMAL COST$

CRASH SLOPE

A

NONE

3

0

60

0

B

NONE

7

1

30

50

C

A

5

3

50

13.33

D

A

6

1

30

20

E

C,B

4

2

40

30

1.What is the normal project duration? = BLANK-1

2. Whatis the normal project cost? = BLANK-2

3. What is the project cost when fully crashed? = BLANK-3

4. Which activities were crashed to reach the final crashed duration? List in order
= BLANK-4

5. What is the project duration when completely crashed? = BLANK-5

Solutions

Expert Solution

PLEASE RATE POSITIVE IF YOU LIKE MY ANSWER TO ENCOURAGE MY EMPLOYMENT

Following is the network diagram

The paths and path-lengths are as follows

A-D =3+6 = 9

A-C-E = 3+5+4 =12

B-E = 7+4 = 11

Hence ACE is the critical path

1. Normal project duration = length of critical path = 12

2. Normal project cost = 60+30+ 50+30+40 = 210

3. Crashing cost = Crash Slope * Crash days = (50*1) + (13.33*3) + (20*1)+ (30*2) = 50+ 40+ 20+ 60 = 170

Therefore, cost when fully crashed = Normal cost + Crashing cost = 210+170 = 380

4.

Activities from critical chain are crashed in order of crashing slope. Out of A-C-E , C has the lowest slope

Activity C is crashed by 3 days. Hence path lengths are

A-D =3+6 = 9

A-C-E = 3+2+4 =9

B-E = 7+4 = 11

Now, B-E is critical path.

E is crashed by two days

Hence path lengths are

A-D =3+6 = 9

A-C-E = 3+2+2 =7

B-E = 7+2 = 9

D and B are crashed by 1 day each in order

Hence path lengths are

A-D =3+5 = 8

A-C-E = 3+2+2 =7

B-E = 6+2 = 8

Hence the order of crashing is  C,E,D,B

5. Project duration after crashing as seen from question 4 is 8 days


Related Solutions

Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
1. The following time estimates are given for an activity: optimistic time = 16 days, most...
1. The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38 days. What is the expected time to complete this activity? Group of answer choices A. 16 B. 24 C. 38 D. 25 E. None of these answers are correct 2. The project duration is equal to the sum of the durations of all activities in a network. Group of answer choices True False 3.The...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT