In: Operations Management
For the given data, crash the project completely.
ACTIVITY |
PREDECESSOR |
NORMAL TIME(DAYS) |
MAX CRASH TIME |
NORMAL COST$ |
CRASH SLOPE |
A |
NONE |
3 |
0 |
60 |
0 |
B |
NONE |
7 |
1 |
30 |
50 |
C |
A |
5 |
3 |
50 |
13.33 |
D |
A |
6 |
1 |
30 |
20 |
E |
C,B |
4 |
2 |
40 |
30 |
1.What is the normal project duration? = BLANK-1
2. Whatis the normal project cost? = BLANK-2
3. What is the project cost when fully crashed? = BLANK-3
4. Which activities were crashed to reach the final crashed
duration? List in order
= BLANK-4
5. What is the project duration when completely crashed? = BLANK-5
PLEASE RATE POSITIVE IF YOU LIKE MY ANSWER TO ENCOURAGE MY EMPLOYMENT
Following is the network diagram
The paths and path-lengths are as follows
A-D =3+6 = 9
A-C-E = 3+5+4 =12
B-E = 7+4 = 11
Hence ACE is the critical path
1. Normal project duration = length of critical path = 12
2. Normal project cost = 60+30+ 50+30+40 = 210
3. Crashing cost = Crash Slope * Crash days = (50*1) + (13.33*3) + (20*1)+ (30*2) = 50+ 40+ 20+ 60 = 170
Therefore, cost when fully crashed = Normal cost + Crashing cost = 210+170 = 380
4.
Activities from critical chain are crashed in order of crashing slope. Out of A-C-E , C has the lowest slope
Activity C is crashed by 3 days. Hence path lengths are
A-D =3+6 = 9
A-C-E = 3+2+4 =9
B-E = 7+4 = 11
Now, B-E is critical path.
E is crashed by two days
Hence path lengths are
A-D =3+6 = 9
A-C-E = 3+2+2 =7
B-E = 7+2 = 9
D and B are crashed by 1 day each in order
Hence path lengths are
A-D =3+5 = 8
A-C-E = 3+2+2 =7
B-E = 6+2 = 8
Hence the order of crashing is C,E,D,B
5. Project duration after crashing as seen from question 4 is 8 days