Question

In: Operations Management

QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...

QUESTION 5

  1. A project has the following activities:

    Activity

    Duration, days

    Predecessor activity

    A

    8

    None

    B

    7

    A

    C

    4

    None

    D

    11

    C

    E

    7

    B & D

    The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8.

    John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period.

    By using the CPM and resource leveling, the project is expected to complete, in earliest date, by the end of Day:

Solutions

Expert Solution


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
8. if the project duration needs to be reduced then a. the activity with the lost...
8. if the project duration needs to be reduced then a. the activity with the lost cost should be selected b. activity which is currently undergoing should be selected c. activity with the highest cost should be selected d. activity on the critical path should be selected . 9. it does not make any sense to crash if a. if there is no critical activity left b. project crashing cost is equal or more than saving c. project is more...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 6 2 1 3 3 15 3 1 3 4 11 4 1 1 2 9 5 2 2 6 7 6 3 3 7 8 7 4 4 6 8 8 5,6 2 3 4 9 8 1 4 7 10 7 3 4 5 11 9,10 5 6 7    b. Indicate the critical path. 1-2-5-8-9-11...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT