QUESTION 5
A project has the following activities:
Activity |
Duration, days |
Predecessor activity |
A |
8 |
None |
B |
7 |
A |
C |
4 |
None |
D |
11 |
C |
E |
7 |
B & D |
The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8.
John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period.
By using the CPM and resource leveling, the project is expected to complete, in earliest date, by the end of Day: