Question

In: Operations Management

Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...

  1. Information on a project’s activities is shown in the following table:

Activity

Immediate Predecessor

Activity Time (wks)

Total Budgeted Cost

A

-

4

24,000

B

-

3

27,000

C

B

2

14,000

D

A

8

32,000

E

D

3

24,000

F

C, E

4

60,000

G

D

6

30,000

H

F

6

30,000

I

G

4

20,000

J

G, H

3

18,000

K

I

2

10,000

L

J

4

16,000

  1. Create a Gantt chart based on earliest start times. (20 pts)

  1. Create a budget cost chart, using earliest start times. (20 pts)

Solutions

Expert Solution

For solving this, first of all you need to calculate the durations based on Earliest Start as shown in the below image;

Gnatt chart is a diagrammatic representation of the durations. It is to be constructed as indicated in the below image;

Now, for preparing the budget, you need to estimate the cost for the activities in accordance with the gnatt chart. Here the total cost is divided by durations to estimate weekly cost.


Related Solutions

A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time...
A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time A - 3 B A 2 C - 5 D B, C 2 E A 4 F B, C 6 G E, D 5 Draw a network for this project? (Marks 0.5) Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 0.5) What are the critical path? (Marks 0.5)
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8 - B 5 7 9 - C 2 4 6 - D 1 2 3 A E 1 4 7 C F 3 6 9 B,D,E G 1 5 9 F H 1 2 3 F I 2 5 8 G,H Draw an AON network based on the given table Determine the expected time for each activity Calculate the ES, EF, LS, LF for...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT