Question

In: Accounting

A value stream has three activities and two products. The units produced and shipped per week...

A value stream has three activities and two products. The units produced and shipped per week are 50 of the deluxe model (Model A) and 150 of the basic model (Model B). The resource consumption patterns are shown as follows: Model A Model B Costs of Value- Stream Activities Cell manufacturing 2,360 min. 7,080 min. $ 94,400 Engineering 65 hrs. 221 hrs. 24,596 Testing 105 hrs. 273 hrs. 26,838 Total $ 145,834

Required:

1. Calculate the ABC product cost for Models A and B. If required, round your answers to the nearest cent.

Product Cost Per Unit

Model A $ per unit

Model B $ per unit

2a. Calculate the value-stream average product cost. If required, round your answer to the nearest cent.
$ per unit

Solutions

Expert Solution

1:Calculate the ABC product cost for Models A and B

Cell manufacturing: Driver is conversion time (in minutes)

=$94,400/(2,360 + 7,080)

= $10 per minute

Engineering: Driver is engineering hours

=$24,596/(65 + 221)

= $86 per engineering hour

Testing: Driver is testing hours:

=$26,838/(105 + 273)

= $71 per test hour

Now calculate product costs as under

Particulars

Model A

Model-B

Cell:(A=10*2,360,B=10*7,080)

23,600

70,800

Engineering:(A=86*65,B=86*221)

5,590

19,006

Testing:(A=71*105,B=71*273)

7,455

19,383

Total   A

36,645

109,189

Units    B

50

150

Unit cost (Cost/Units) A/B

$732.9

$727.93

2-a

Average cost = $145,834/200

= $729.17

The average cost approximates the ABC costs with very little error, suggesting that the two value-stream products are quite similar. Alternatively, the ABC cost is about the same for each model, suggesting significant homogeneity and thus the correct specification of the value stream


Related Solutions

A value stream has three activities and two products. The units produced and shipped per week...
A value stream has three activities and two products. The units produced and shipped per week are 50 of the deluxe model (Model A) and 150 of the basic model (Model B). The resource consumption patterns are shown as follows: Model A Model B Costs of Value- Stream Activities Cell manufacturing 2,380 min. 7,140 min. $ 57,120 Engineering 65 hrs. 234 hrs. 26,013 Testing 95 hrs. 247 hrs. 27,360    Total $ 110,493 Required: 1. Calculate the ABC product cost for...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units of its aluminum wheels: 4,000 units of Model A and 12,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,600                      $19,600 Production planning        236,400                      236,400 Purchasing        23,400                      23,400 Stamping $380,000        38,000        $37,000        $20,000        475,000...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 15,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 15,400 units of its aluminum wheels: 3,000 units of Model A and 12,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,000                      $19,000 Production planning        243,000                      243,000 Purchasing        22,500                      22,500 Stamping $355,000        35,500        $36,600        $20,000        447,100...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,000 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,000 units of its aluminum wheels: 3,400 units of Model A and 12,600 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,400                      $19,400 Production planning        34,800                      34,800 Purchasing        23,400                      23,400 Stamping $380,000        38,000        $36,200        $18,000        472,200...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 17,200 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 17,200 units of its aluminum wheels: 3,800 units of Model A and 13,400 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $20,000                      $20,000 Production planning        228,600                      228,600 Purchasing        22,500                      22,500 Stamping $365,000        36,500        $37,400        $20,000        458,900...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 18,000 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 18,000 units of its aluminum wheels: 5,000 units of Model A and 13,000 units of Model B. The following costs were incurred: Materials        Salaries/ Wages        Machining        Other        Total Cost Order processing        $19,000                      $19,000 Production planning        199,800                      199,800 Purchasing        25,200                      25,200 Stamping $355,000        35,500        $37,800        $19,600        447,900...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units...
Value-Stream Costing Objective During the week of June 12, Harrison Manufacturing produced and shipped 16,400 units of its aluminum wheels: 3,600 units of Model A and 12,800 units of Model B. The following costs were incurred: Materials Salaries/ Wages Machining Other Total Cost Order processing $19,400 $19,400 Production planning 304,800 304,800 Purchasing 23,400 23,400 Stamping $380,000 38,000 $37,200 $19,200 474,400 Welding 160,000 20,000 16,000 12,000 208,000 Cladding 65,000 65,000 Testing 10,000 10,000 Packaging and shipping 10,000 10,000 Invoicing 14,200 14,200...
Value-Stream Average Costing, ABC Costs as Benchmarks A value stream has three activities and two products....
Value-Stream Average Costing, ABC Costs as Benchmarks A value stream has three activities and two products. The units produced and shipped per week are 50 of the deluxe model (Model A) and 150 of the basic model (Model B). The resource consumption patterns are shown as follows: Model A Model B Costs of Value- Stream Activities Cell manufacturing 2,400 min. 7,200 min. $ 76,800 Engineering 60 hrs. 260 hrs. 27,200 Testing 100 hrs. 220 hrs. 24,000 Total $ 128,000 Required:...
Ohio Logistics manages the logistical activities for firms by matching companies that need products shipped with...
Ohio Logistics manages the logistical activities for firms by matching companies that need products shipped with carriers that can provide the best rates and best service for the companies. Ohio Logistics is very concerned that its carriers deliver their customers' material on time, so it carefully monitors the percentage of on-time deliveries. The following table contains a list of the carriers used by Ohio Logistics and the corresponding on-time percentages for the current and previous year. SEE BELOW to reference...
48. Tanner Corporation produced 5,490 units, consisting of three separate products, in a joint process for...
48. Tanner Corporation produced 5,490 units, consisting of three separate products, in a joint process for the year. The market for these products was so unstable that it was not practical to estimate the selling price of the products. A cost of $499,000 was incurred in the joint process. Product X's production was 80% of product Y's while product Z's production was 125% of product Y's. What is the amount of the joint cost allocable to product X assuming Tanner...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT