In: Operations Management
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic .
Activity time(week) |
Activity Cost($) |
|||
Activity |
Normal |
Crash |
Normal |
Crash |
a |
9 |
7 |
$4,800 |
$6,300 |
b |
11 |
9 |
$9,100 |
$15,500 |
c |
7 |
5 |
$3,000 |
$4,000 |
d |
10 |
8 |
$3,600 |
$5,000 |
e |
1 |
1 |
$0 |
$0 |
f |
5 |
3 |
$1,500 |
$2,000 |
g |
6 |
5 |
$1,800 |
$2,000 |
h |
3 |
3 |
$0 |
$0 |
i |
1 |
1 |
$0 |
$0 |
j |
2 |
2 |
$0 |
$0 |
k |
8 |
6 |
$5,000 |
$7,000 |
Crash the network the maximum amount , indicate how much it would cost the bank and identify the critical path(s). “ don’t use any software, solve the problem manually with explaining the steps “.
Above details are based on :
A bank is planning to install a new computerized accounts system. Bank management has
determined the activities required to complete the project, the precedence relationships of
the activities, and activity time estimates as follows:
Time Estimates |
|||||
Activity |
Description |
Predecessor |
a |
m |
b |
a |
Position recruting |
- |
5 |
8 |
17 |
b |
system development |
- |
3 |
12 |
15 |
c |
system training |
a |
4 |
7 |
10 |
d |
equpiment training |
a |
5 |
8 |
23 |
e |
manual system test |
b,c |
1 |
1 |
1 |
f |
preliminary system change over |
b,c |
1 |
4 |
13 |
g |
computre-personnel interface |
d,e |
3 |
6 |
9 |
h |
equpiment modification |
d,e |
1 |
2.5 |
7 |
i |
equipment testing |
h |
1 |
1 |
1 |
j |
system debugging nd installation |
f,g |
2 |
2 |
2 |
k |
equipment changeover |
g,i |
5 |
8 |
11 |
We will first calculate expected time for each activity by using formula
Te= (a+4*m+b)/ 6
Time Estimates | ||||||
Activity | Description | Predecessor | a | m | b | Expected time |
a | Position recruting | - | 5 | 8 | 17 | (5+4*8+17)/6=9 |
b | system development | - | 3 | 12 | 15 | 11 |
c | system training | a | 4 | 7 | 10 | 7 |
d | equpiment training | a | 5 | 8 | 23 | 10 |
e | manual system test | b,c | 1 | 1 | 1 | 1 |
f | preliminary system change over | b,c | 1 | 4 | 13 | 5 |
g | computre-personnel interface | d,e | 3 | 6 | 9 | 6 |
h | equpiment modification | d,e | 1 | 2.5 | 7 | 3 |
i | equipment testing | h | 1 | 1 | 1 | 1 |
j | system debugging nd installation | f,g | 2 | 2 | 2 | 2 |
k | equipment changeover | g,i | 5 | 8 | 11 | 8 |
We will draw network diagram and then find critical path. Critical path is the path with longest completion time among alll possible paths.
Possible paths:
Hence, critical path is a-d-g-k with total project duration of 33 weeks (same as critical path)
For crashing the project, we will first calculate crash slope for all activities by using formula
Crash slope = (Crash cost - Normal cost)/ (Normal time - crash time)
Activity time(week) | Activity Cost($) | ||||
Activity | Normal | Crash | Normal | Crash | Crash slope |
a | 9 | 7 | $4,800 | $6,300 | (6300-4800)/(9-7)=750 |
b | 11 | 9 | $9,100 | $15,500 | 3200 |
c | 7 | 5 | $3,000 | $4,000 | 500 |
d | 10 | 8 | $3,600 | $5,000 | 700 |
e | 1 | 1 | $0 | $0 | |
f | 5 | 3 | $1,500 | $2,000 | 250 |
g | 6 | 5 | $1,800 | $2,000 | 200 |
h | 3 | 3 | $0 | $0 | |
i | 1 | 1 | $0 | $0 | |
j | 2 | 2 | $0 | $0 | |
k | 8 | 6 | $5,000 | $7,000 | 1000 |
Now we will crash activities on critical path to reduce the project duration. We will first crash activities with lowest crash slope.
- On critical path a-d-g-k, the activity g has lowest crash slope ($200) and will be crashed first by 1 week. Project duration is now 32 weeks. Total crash cost is $200.
- On critical path a-d-g-k, next we will crash activity d ($700) by 1 week as it has lowest crash slope since activity g cannot be crashed further. Project duration is now 31 weeks. Total crash cost is $200+$700=$900. Critical path is still same a-d-g-k
- On critical path a-d-g-k, next we will crash activity d ($700) by second week as it has lowest crash slope. Project duration is now 30 weeks. Total crash cost is 900+700=$1600. Critical paths are a-d-g-k and a-c-e-g-k
- Next we will crash activity a ($750 each) by two week as it is common activity and lowest cost slope. Project duration is now 28 weeks. Total crash cost is $1600+750*2=3100. Critical paths are a-d-g-k and a-c-e-g-k
- Next we will crash activity k (1000 each) by two week as it is common activity and lowest cost slope. Project duration is now 26 weeks. Total crash cost is $3100+1000*2=5100. Critical paths are a-d-g-k and a-c-e-g-k
This is maximum crashing which is possible since have crashed all possible activity on critical path (a-d-g-k ) to maximum crashing limit.
Hence, the final crashed project duration is 26 weeks. Total minimum crashing cost is $5,100. Two critical paths are a-d-g-k and a-c-e-g-k
Please give thumbs up/ likes if the answer is helpful. Thank
you!