Question

In: Operations Management

The following table provides the crash data for the project network . the normal activity times...

The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic .

Activity time(week)

Activity Cost($)

Activity

Normal

Crash

Normal

Crash

a

9

7

$4,800

$6,300

b

11

9

$9,100

$15,500

c

7

5

$3,000

$4,000

d

10

8

$3,600

$5,000

e

1

1

$0

$0

f

5

3

$1,500

$2,000

g

6

5

$1,800

$2,000

h

3

3

$0

$0

i

1

1

$0

$0

j

2

2

$0

$0

k

8

6

$5,000

$7,000

Crash the network the maximum amount , indicate how much it would cost the bank and identify the critical path(s). “ don’t use any software, solve the problem manually with explaining the steps “.

Above details are based on :

A bank is planning to install a new computerized accounts system. Bank management has

determined the activities required to complete the project, the precedence relationships of

the activities, and activity time estimates as follows:

Time Estimates

Activity

Description

Predecessor

a

m

b

a

Position recruting

-

5

8

17

b

system development

-

3

12

15

c

system training

a

4

7

10

d

equpiment training

a

5

8

23

e

manual system test

b,c

1

1

1

f

preliminary system change over

b,c

1

4

13

g

computre-personnel interface

d,e

3

6

9

h

equpiment modification

d,e

1

2.5

7

i

equipment testing

h

1

1

1

j

system debugging nd installation

f,g

2

2

2

k

equipment changeover

g,i

5

8

11

Solutions

Expert Solution

We will first calculate expected time for each activity by using formula

Te= (a+4*m+b)/ 6

Time Estimates
Activity Description Predecessor a m b Expected time
a Position recruting - 5 8 17 (5+4*8+17)/6=9
b system development - 3 12 15 11
c system training a 4 7 10 7
d equpiment training a 5 8 23 10
e manual system test b,c 1 1 1 1
f preliminary system change over b,c 1 4 13 5
g computre-personnel interface d,e 3 6 9 6
h equpiment modification d,e 1 2.5 7 3
i equipment testing h 1 1 1 1
j system debugging nd installation f,g 2 2 2 2
k equipment changeover g,i 5 8 11 8

We will draw network diagram and then find critical path. Critical path is the path with longest completion time among alll possible paths.

Possible paths:

  • a-d-h-i-k: 9+10+3+1+8=31
  • a-d-g-k:33
  • a-d-g-j:27
  • a-c-e-h-i-k:29
  • a-c-e-g-k:31
  • a-c-e-g-j:25
  • a-c-f-j:23
  • b-e-h-i-k:24
  • b-e-g-k:26
  • b-e-g-j:20
  • b-f-j:18

Hence, critical path is a-d-g-k with total project duration of 33 weeks (same as critical path)

For crashing the project, we will first calculate crash slope for all activities by using formula

Crash slope = (Crash cost - Normal cost)/ (Normal time - crash time)

Activity time(week) Activity Cost($)
Activity Normal Crash Normal Crash Crash slope
a 9 7 $4,800 $6,300 (6300-4800)/(9-7)=750
b 11 9 $9,100 $15,500 3200
c 7 5 $3,000 $4,000 500
d 10 8 $3,600 $5,000 700
e 1 1 $0 $0
f 5 3 $1,500 $2,000 250
g 6 5 $1,800 $2,000 200
h 3 3 $0 $0
i 1 1 $0 $0
j 2 2 $0 $0
k 8 6 $5,000 $7,000 1000

Now we will crash activities on critical path to reduce the project duration. We will first crash activities with lowest crash slope.

- On critical path a-d-g-k, the activity g has lowest crash slope ($200) and will be crashed first by 1 week. Project duration is now 32 weeks. Total crash cost is $200.

- On critical path a-d-g-k, next we will crash activity d ($700) by 1 week as it has lowest crash slope since activity g cannot be crashed further. Project duration is now 31 weeks. Total crash cost is $200+$700=$900. Critical path is still same a-d-g-k

- On critical path a-d-g-k, next we will crash activity d ($700) by second week as it has lowest crash slope. Project duration is now 30 weeks. Total crash cost is 900+700=$1600. Critical paths are a-d-g-k and a-c-e-g-k

- Next we will crash activity a ($750 each) by two week as it is common activity and lowest cost slope. Project duration is now 28 weeks. Total crash cost is $1600+750*2=3100. Critical paths are a-d-g-k and a-c-e-g-k

- Next we will crash activity k (1000 each) by two week as it is common activity and lowest cost slope. Project duration is now 26 weeks. Total crash cost is $3100+1000*2=5100. Critical paths are a-d-g-k and a-c-e-g-k

This is maximum crashing which is possible since have crashed all possible activity on critical path (a-d-g-k ) to maximum crashing limit.

Hence, the final crashed project duration is 26 weeks. Total minimum crashing cost is $5,100. Two critical paths are a-d-g-k and a-c-e-g-k


Please give thumbs up/ likes if the answer is helpful. Thank you!


Related Solutions

The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
The following table provides data for a project. Use the data to answer the following questions...
The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic Most Likely Pessimistic Expected Variance A - 6 7 14 B - 8 10 12 C A 2 3 4 D A 6 7 8 E B,C 5 5.5 9 F B,C 5 7 9 G D,E 4 6 8 H F 2.5 3 3.5 Draw a network to represent the above project. What is the critical...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days.
Supplemental assignment for MGMT8300: Network Diagram and the Critical Path 1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days. 2. What is the critical path? 3. How long will it take to complete the project if everything goes according to plan? 4. Choose an activity that is not on the critical path. How many days longer should it take in order for the critical...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 6 8 10 B A 1 2 4 C A 9 12 15 D A 3 4 5 E B 4 6 7 F B 14 16 22 G C, D 2 3 4 H E, G 1 2 3 I G 6 8 9 J H, I 4 6 8 K F, H, J 1 2 5 a. Draw the...
Given the following information, compute the early, late, and slack times for the project network.
Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?
Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT