In: Operations Management
|
Activity |
Normal Time (days) |
Normal Cost ($) |
Crash Time (days) |
Crash Cost ($) |
Immediate Predecessor(s) |
|
A |
6 |
1,000 |
5 |
1,200 |
— |
|
B |
4 |
800 |
2 |
2,000 |
— |
|
C |
3 |
600 |
2 |
900 |
A, B |
|
D |
2 |
1,500 |
1 |
2,000 |
B |
|
E |
6 |
900 |
4 |
1,200 |
C, D |
|
F |
2 |
1,300 |
1 |
1,400 |
E |
|
G |
4 |
900 |
4 |
900 |
E |
|
H |
4 |
500 |
2 |
900 |
G |
Please complete in excel and not in a
notebook.



(Note: please like the answer it will encourage me. Do comment if any correction required before disliking.)