In: Statistics and Probability
Time (days) |
Immediate |
Time (days) |
Immediate |
||||||||||||
Activity |
a |
m |
b |
Predecessor(s) |
Activity |
a |
m |
b |
Predecessor(s) |
||||||
A |
55 |
55 |
77 |
long dash— |
H |
44 |
44 |
66 |
E, F |
||||||
B |
11 |
22 |
55 |
long dash— |
I |
22 |
77 |
1010 |
G, H |
||||||
C |
55 |
55 |
55 |
A |
J |
22 |
44 |
77 |
I |
||||||
D |
44 |
88 |
1313 |
A |
K |
66 |
1010 |
1313 |
I |
||||||
E |
11 |
1010 |
1717 |
B, C |
L |
22 |
66 |
66 |
J |
||||||
F |
11 |
55 |
77 |
D |
M |
22 |
22 |
33 |
K |
||||||
G |
22 |
66 |
99 |
D |
N |
77 |
77 |
1212 |
L, M |
b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 55 days or less =
from abve:
as std deviaiton =(b-a)/6
hence
Activity | Optimistic | Likely | Pessimistic | Mean | Std dev | ||
A | 5 | 5 | 7 | 5.33 | 0.33 | ||
B | 1 | 2 | 5 | 2.33 | 0.67 | ||
C | 5 | 5 | 5 | 5.00 | 0.00 | ||
D | 4 | 8 | 13 | 8.17 | 1.50 | ||
E | 1 | 10 | 17 | 9.67 | 2.67 | ||
F | 1 | 5 | 7 | 4.67 | 1.00 | ||
G | 2 | 6 | 9 | 5.83 | 1.17 | ||
H | 4 | 4 | 6 | 4.33 | 0.33 | ||
I | 2 | 7 | 10 | 6.67 | 1.33 | ||
J | 2 | 4 | 7 | 4.17 | 0.83 | ||
K | 6 | 10 | 13 | 9.83 | 1.17 | ||
L | 2 | 6 | 6 | 5.33 | 0.67 | ||
M | 2 | 2 | 3 | 2.17 | 0.17 | ||
N | 7 | 7 | 12 | 7.83 | 0.83 |
Activity | Early Start | Early Finish | Late Start | Late Finish | Slack |
A | 0.00 | 5.33 | 0.00 | 5.33 | 0.00 |
B | 0.00 | 2.33 | 8.00 | 10.33 | 8.00 |
C | 5.33 | 10.33 | 5.33 | 10.33 | 0.00 |
D | 5.33 | 13.50 | 7.17 | 15.33 | 1.83 |
E | 10.33 | 20.00 | 10.33 | 20.00 | 0.00 |
F | 13.50 | 18.17 | 15.33 | 20.00 | 1.83 |
G | 13.50 | 19.33 | 18.50 | 24.33 | 5.00 |
H | 20.00 | 24.33 | 20.00 | 24.33 | 0.00 |
I | 24.33 | 31.00 | 24.33 | 31.00 | 0.00 |
J | 31.00 | 35.17 | 33.50 | 37.67 | 2.50 |
K | 31.00 | 40.83 | 31.00 | 40.83 | 0.00 |
L | 35.17 | 40.50 | 37.67 | 43.00 | 2.50 |
M | 40.83 | 43.00 | 40.83 | 43.00 | 0.00 |
N | 43.00 | 50.83 | 43.00 | 50.83 | 0.00 |
as acticvity on crtical path (with ) slack are =A ,C ,E ,H , I ,K M,N
thereofre project std deviation=sqrt(sum of variance of activiities on critical path)
=sqrt(11.194) =3.346
hence probability that the critical path will be finished in 55 days or less =P(X<55)
=P(Z<(55-50.83)/3.346)=P(Z<1.25)=0.8944