Question

In: Statistics and Probability

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...

Time​ (days)

Immediate

Time​ (days)

Immediate

Activity

a

m

b

​Predecessor(s)

Activity

a

m

b

​Predecessor(s)

A

55

55

77

long dash—

H

44

44

66

​E, F

B

11

22

55

long dash—

I

22

77

1010

​G, H

C

55

55

55

A

J

22

44

77

I

D

44

88

1313

A

K

66

1010

1313

I

E

11

1010

1717

​B, C

L

22

66

66

J

F

11

55

77

D

M

22

22

33

K

G

22

66

99

D

N

77

77

1212

​L, M

b) If the time to complete the activities on the critical path is normally​ distributed, then the probability that the critical path will be finished in 55 days or less​ =

Solutions

Expert Solution

from abve:

as std deviaiton =(b-a)/6

hence

Activity Optimistic Likely Pessimistic Mean Std dev
A 5 5 7 5.33 0.33
B 1 2 5 2.33 0.67
C 5 5 5 5.00 0.00
D 4 8 13 8.17 1.50
E 1 10 17 9.67 2.67
F 1 5 7 4.67 1.00
G 2 6 9 5.83 1.17
H 4 4 6 4.33 0.33
I 2 7 10 6.67 1.33
J 2 4 7 4.17 0.83
K 6 10 13 9.83 1.17
L 2 6 6 5.33 0.67
M 2 2 3 2.17 0.17
N 7 7 12 7.83 0.83
Activity Early Start Early Finish Late Start Late Finish Slack
A 0.00 5.33 0.00 5.33 0.00
B 0.00 2.33 8.00 10.33 8.00
C 5.33 10.33 5.33 10.33 0.00
D 5.33 13.50 7.17 15.33 1.83
E 10.33 20.00 10.33 20.00 0.00
F 13.50 18.17 15.33 20.00 1.83
G 13.50 19.33 18.50 24.33 5.00
H 20.00 24.33 20.00 24.33 0.00
I 24.33 31.00 24.33 31.00 0.00
J 31.00 35.17 33.50 37.67 2.50
K 31.00 40.83 31.00 40.83 0.00
L 35.17 40.50 37.67 43.00 2.50
M 40.83 43.00 40.83 43.00 0.00
N 43.00 50.83 43.00 50.83 0.00

as acticvity on crtical path (with ) slack are =A ,C ,E ,H , I ,K M,N

thereofre project std deviation=sqrt(sum of variance of activiities on critical path)

=sqrt(11.194) =3.346

hence probability that the critical path will be finished in 55 days or less​ =P(X<55)

=P(Z<(55-50.83)/3.346)=P(Z<1.25)=0.8944


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT