In: Statistics and Probability
| 
 Time (days)  | 
 Immediate  | 
 Time (days)  | 
 Immediate  | 
||||||||||||
| 
 Activity  | 
 a  | 
 m  | 
 b  | 
 Predecessor(s)  | 
 Activity  | 
 a  | 
 m  | 
 b  | 
 Predecessor(s)  | 
||||||
| 
 A  | 
 55  | 
 55  | 
 77  | 
 long dash—  | 
 H  | 
 44  | 
 44  | 
 66  | 
 E, F  | 
||||||
| 
 B  | 
 11  | 
 22  | 
 55  | 
 long dash—  | 
 I  | 
 22  | 
 77  | 
 1010  | 
 G, H  | 
||||||
| 
 C  | 
 55  | 
 55  | 
 55  | 
 A  | 
 J  | 
 22  | 
 44  | 
 77  | 
 I  | 
||||||
| 
 D  | 
 44  | 
 88  | 
 1313  | 
 A  | 
 K  | 
 66  | 
 1010  | 
 1313  | 
 I  | 
||||||
| 
 E  | 
 11  | 
 1010  | 
 1717  | 
 B, C  | 
 L  | 
 22  | 
 66  | 
 66  | 
 J  | 
||||||
| 
 F  | 
 11  | 
 55  | 
 77  | 
 D  | 
 M  | 
 22  | 
 22  | 
 33  | 
 K  | 
||||||
| 
 G  | 
 22  | 
 66  | 
 99  | 
 D  | 
 N  | 
 77  | 
 77  | 
 1212  | 
 L, M  | 
||||||
b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 55 days or less =
from abve:
as std deviaiton =(b-a)/6
hence
| Activity | Optimistic | Likely | Pessimistic | Mean | Std dev | ||
| A | 5 | 5 | 7 | 5.33 | 0.33 | ||
| B | 1 | 2 | 5 | 2.33 | 0.67 | ||
| C | 5 | 5 | 5 | 5.00 | 0.00 | ||
| D | 4 | 8 | 13 | 8.17 | 1.50 | ||
| E | 1 | 10 | 17 | 9.67 | 2.67 | ||
| F | 1 | 5 | 7 | 4.67 | 1.00 | ||
| G | 2 | 6 | 9 | 5.83 | 1.17 | ||
| H | 4 | 4 | 6 | 4.33 | 0.33 | ||
| I | 2 | 7 | 10 | 6.67 | 1.33 | ||
| J | 2 | 4 | 7 | 4.17 | 0.83 | ||
| K | 6 | 10 | 13 | 9.83 | 1.17 | ||
| L | 2 | 6 | 6 | 5.33 | 0.67 | ||
| M | 2 | 2 | 3 | 2.17 | 0.17 | ||
| N | 7 | 7 | 12 | 7.83 | 0.83 | 
| Activity | Early Start | Early Finish | Late Start | Late Finish | Slack | 
| A | 0.00 | 5.33 | 0.00 | 5.33 | 0.00 | 
| B | 0.00 | 2.33 | 8.00 | 10.33 | 8.00 | 
| C | 5.33 | 10.33 | 5.33 | 10.33 | 0.00 | 
| D | 5.33 | 13.50 | 7.17 | 15.33 | 1.83 | 
| E | 10.33 | 20.00 | 10.33 | 20.00 | 0.00 | 
| F | 13.50 | 18.17 | 15.33 | 20.00 | 1.83 | 
| G | 13.50 | 19.33 | 18.50 | 24.33 | 5.00 | 
| H | 20.00 | 24.33 | 20.00 | 24.33 | 0.00 | 
| I | 24.33 | 31.00 | 24.33 | 31.00 | 0.00 | 
| J | 31.00 | 35.17 | 33.50 | 37.67 | 2.50 | 
| K | 31.00 | 40.83 | 31.00 | 40.83 | 0.00 | 
| L | 35.17 | 40.50 | 37.67 | 43.00 | 2.50 | 
| M | 40.83 | 43.00 | 40.83 | 43.00 | 0.00 | 
| N | 43.00 | 50.83 | 43.00 | 50.83 | 0.00 | 
as acticvity on crtical path (with ) slack are =A ,C ,E ,H , I ,K M,N
thereofre project std deviation=sqrt(sum of variance of activiities on critical path)
=sqrt(11.194) =3.346
hence probability that the critical path will be finished in 55 days or less =P(X<55)
=P(Z<(55-50.83)/3.346)=P(Z<1.25)=0.8944