Question

In: Statistics and Probability

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...

Time​ (days)

Immediate

Time​ (days)

Immediate

Activity

a

m

b

​Predecessor(s)

Activity

a

m

b

​Predecessor(s)

A

55

55

77

long dash—

H

44

44

66

​E, F

B

11

22

55

long dash—

I

22

77

1010

​G, H

C

55

55

55

A

J

22

44

77

I

D

44

88

1313

A

K

66

1010

1313

I

E

11

1010

1717

​B, C

L

22

66

66

J

F

11

55

77

D

M

22

22

33

K

G

22

66

99

D

N

77

77

1212

​L, M

b) If the time to complete the activities on the critical path is normally​ distributed, then the probability that the critical path will be finished in 55 days or less​ =

Solutions

Expert Solution

from abve:

as std deviaiton =(b-a)/6

hence

Activity Optimistic Likely Pessimistic Mean Std dev
A 5 5 7 5.33 0.33
B 1 2 5 2.33 0.67
C 5 5 5 5.00 0.00
D 4 8 13 8.17 1.50
E 1 10 17 9.67 2.67
F 1 5 7 4.67 1.00
G 2 6 9 5.83 1.17
H 4 4 6 4.33 0.33
I 2 7 10 6.67 1.33
J 2 4 7 4.17 0.83
K 6 10 13 9.83 1.17
L 2 6 6 5.33 0.67
M 2 2 3 2.17 0.17
N 7 7 12 7.83 0.83
Activity Early Start Early Finish Late Start Late Finish Slack
A 0.00 5.33 0.00 5.33 0.00
B 0.00 2.33 8.00 10.33 8.00
C 5.33 10.33 5.33 10.33 0.00
D 5.33 13.50 7.17 15.33 1.83
E 10.33 20.00 10.33 20.00 0.00
F 13.50 18.17 15.33 20.00 1.83
G 13.50 19.33 18.50 24.33 5.00
H 20.00 24.33 20.00 24.33 0.00
I 24.33 31.00 24.33 31.00 0.00
J 31.00 35.17 33.50 37.67 2.50
K 31.00 40.83 31.00 40.83 0.00
L 35.17 40.50 37.67 43.00 2.50
M 40.83 43.00 40.83 43.00 0.00
N 43.00 50.83 43.00 50.83 0.00

as acticvity on crtical path (with ) slack are =A ,C ,E ,H , I ,K M,N

thereofre project std deviation=sqrt(sum of variance of activiities on critical path)

=sqrt(11.194) =3.346

hence probability that the critical path will be finished in 55 days or less​ =P(X<55)

=P(Z<(55-50.83)/3.346)=P(Z<1.25)=0.8944


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
You are given the following table Activity a m b Immediate Predecessor A 2 5 8...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8 - B 5 7 9 - C 2 4 6 - D 1 2 3 A E 1 4 7 C F 3 6 9 B,D,E G 1 5 9 F H 1 2 3 F I 2 5 8 G,H Draw an AON network based on the given table Determine the expected time for each activity Calculate the ES, EF, LS, LF for...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time...
A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time A - 3 B A 2 C - 5 D B, C 2 E A 4 F B, C 6 G E, D 5 Draw a network for this project? (Marks 0.5) Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 0.5) What are the critical path? (Marks 0.5)
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL...
For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL COST$ CRASH SLOPE A NONE 3 0 60 0 B NONE 7 1 30 50 C A 5 3 50 13.33 D A 6 1 30 20 E C,B 4 2 40 30 1.What is the normal project duration? = BLANK-1 2. Whatis the normal project cost? = BLANK-2 3. What is the project cost when fully crashed? = BLANK-3 4. Which activities were...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT