Question

In: Operations Management

Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...

Project management

Expediting a Project

Task

Predecessor

Normal Time Weeks

Normal Cost

Crash Time

Crash Cost

A

-

4

$2000

4

-

B

A

4

$1500

2

4500

C

A

6

5000

4

8000

D

B

2

1000

2

-

E

B

6

8000

3

10000

F

C

10

10000

7

14000

G

D

7

3500

4

5000

H

E

4

2500

2

5000

I

G,H

3

2000

2

3500

J

I,F

3

3000

1

4500

Consider the project shown above.

a)Draw the network diagram and find the critical path, time and cost for an all-normal level of project activity.

b)Calculate the crash cost-per-week assuming that all activities may be partially crashed.

c)Which tasks should be crashed to do the project in 21 weeks? What is the project cost?

d)Calculate the shortest delivery time for the project. What is the cost?

Solutions

Expert Solution

(i)

Critical path is ABEHIJ with duration 24 weeks.

cost for nromal time =38500

(ii)

Activity slope Max crash
A None 0
B 1500 2
C 1500 2
D None 0
E 666.66 3
F 1333.33 3
G 500 3
H 1250 2
I 1500 1
J 750 2

crashing schedule

(i) E is the cheapest activity which can be crashed for a week at 666 per week. Duration is 23 and cost is 38500+666 =39166

Now ABDGIJ, ABEHIJ and ACFJ are critical paths.

(ii) J can be crashed for 2 weeks at a total cost of 1500. Duration is now 21 weeks and cost is 40666

The cost for crashing the project to 21 days is 2166. Total cost is 40666.

(iii) G, E and F can be crashed at a total cost of 2500. Duration is 20

Total cost is 43166

(iv) G, E and F can be again crashed at a total cost of 2500. Duration is 19

Total cost is 45666

(v) B and f can be crashed for 1 day each at a total cost of 2833, Duration is 18

Total cost is 48000

(vi) B and C can be crashed for 1 day at a cost of 3000. Duration is 17

Total cost is 51000.

(vii) C and I can be crashed at a total cost of 3000. Duration is 16

Cost is 54000.

No more crashing is possible.


Related Solutions

The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk...
a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack A 5 - 4 $50 B 3 - 2 $10 C 6 A 3 $2,500 D 3 A 1 $10 E 8 C,B 7 $200 F 3 D,E 1 $1,000 G 4 F 4 - Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack A...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
Given the following project: Act.          Preceding                    Crash Cost    &nbs
Given the following project: Act.          Preceding                    Crash Cost              Maximum Crash               Normal Time                                            Activity                       (in million $)             Time (in months)               (in months) A                     -                                   0                                  0                                  1         B                     A                                 10                                2                                   3                      C                     A                                  5                                 1                                   4                      D                     B                                  6                                 1                                   3                      E                      C                                 7                                  2                                  4                      F                     D, E                                9                                 1                                      3 SLACK TIME = Late Starting Time – Early Starting Time OR Late Finish Time – Early Finish Time To reduce the project time as much as possible given its characteristics, what activity or activities can be crashed?
The Time Numbers represent weeks a. Find the mean time for completion of the project b....
The Time Numbers represent weeks a. Find the mean time for completion of the project b. Find the probability that the project will be completed two weeks earlier than the mean time. Preceding Optimistic Most Likely Pessimistic Activity Activity Time Time Time A. Write Book 10 13 17 B. Design Book Cover A 1 1 1 C. Edit Manuscript A 3 6 9 D. Check Editing C 2 3 6 E. Accept Design B 1 1 1 F. Copy Edit...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT