Question

In: Finance

A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...

A network consists of the following list. Times are given in weeks.

Activity

Preceding

Optimistic

Probable

Pessimistic

A

--

6

8

10

B

A

1

2

4

C

A

9

12

15

D

A

3

4

5

E

B

4

6

7

F

B

14

16

22

G

C, D

2

3

4

H

E, G

1

2

3

I

G

6

8

9

J

H, I

4

6

8

K

F, H, J

1

2

5

a. Draw the network diagram.

b. Calculate the expected duration and variance of each activity.

c. Calculate the expected duration and variance of the critical path

d. Calculate the probability that the project will be completed in less than 42 weeks.

Solutions

Expert Solution

(a) Network Diagram -

(b) Expected Duration of each activity = ( Pessimistic Duration + 4*Probable + Optimistic Duration ) / 6

Variance of Each activity = σ2 = { (Pessimistic Duration - Optimistic Duration) / 6 }2

Standard Deviation of each activity = √σ2 = (Pessimistic Duration - Optimistic Duration) / 6

Activity Predecessor Optimistic Probable Pessimistic Expected Variance Std Dev
A - 6 8 10 8.00 0.444 0.667
B A 1 2 4 2.17 0.250 0.500
C A 9 12 15 12.00 1.000 1.000
D A 3 4 5 4.00 0.111 0.333
E B 4 6 7 5.83 0.250 0.500
F B 14 16 22 16.67 1.778 1.333
G C, D 2 3 4 3.00 0.111 0.333
H E, G 1 2 3 2.00 0.111 0.333
I G 6 8 9 7.83 0.250 0.500
J H, I 4 6 8 6.00 0.444 0.667
K F, H, J 1 2 5 2.33 0.444 0.667

(c) Possible Network Path and their Duration are -

Path Duration
ABFK 29.17
ABEHK 20.33
ABEHJK 26.33
ACGHK 27.33
ACGHJK 33.33
ACGIJK 39.17
ADGHK 19.33
ADGHJK 25.33
ADGIJK 31.17

The critical path is the path with longest duration = ACGIJK with expected duration of 39.17

Variance of critical path ACGIJK = 0.444 + 1.000 + 0.111 + 0.250 + 0.444 + 0.444 = 2.693

(d)

project duration is 39.17 time units

Standard deviation of critical path = √variance = √2.693 = 1.641

So, µ = 39.17, σ = 1.64

Probability that the project will be completed in less than 42 weeks = P(z)

z = ( x - µ )/ σ = (42 - 39.17)/1.64 = 1.73

From the z table, P(z) = 0.9582

Hence probability that the project will be completed in fewer than 30 time units is 95.82%


Related Solutions

A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10...
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none B 2 5 9 A C 4 6 12 A D 5 6 10 B E 6 10 17 C F 3 4 6 D,E G 3 6 10 D,E H 5 7 10 F I 5 8 11 G J 3 3 3 H,I (a) Calculate the expected completion time for this project. (Round...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
1. The following time estimates are given for an activity: optimistic time = 16 days, most...
1. The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38 days. What is the expected time to complete this activity? Group of answer choices A. 16 B. 24 C. 38 D. 25 E. None of these answers are correct 2. The project duration is equal to the sum of the durations of all activities in a network. Group of answer choices True False 3.The...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT