Question

In: Operations Management

The following table provides data for a project. Use the data to answer the following questions...

The following table provides data for a project. Use the data to answer the following questions

Activity

Immediate

Predecessor

Time Estimates (weeks)

Optimistic

Most Likely

Pessimistic

Expected

Variance

A

-

6

7

14

B

-

8

10

12

C

A

2

3

4

D

A

6

7

8

E

B,C

5

5.5

9

F

B,C

5

7

9

G

D,E

4

6

8

H

F

2.5

3

3.5

  1. Draw a network to represent the above project.
  2. What is the critical path? What is the expected completion time? What is the variance of the project completion time? (Complete the expected task time and variance of time calculations.)
  3. The project manager realizes that it is best to take at least 20 weeks to complete the project. However, she also thinks that delaying the project past 26 weeks will result in considerable loss for the company. What is the probability that it will take between 20 and 26 weeks to complete the project?
  4. For the next two parts, assume that the expected times you calculated are the deterministic single point estimates of time. Because of work in other projects, the manager realizes that is very likely that activity B will take 5 more weeks than initially determined. What is the new completion time for the project, given this information?
  5. The manager wants to reduce the project time by two weeks. How can this be achieved? What are the implications? (Answer this question conceptually.)

Solutions

Expert Solution

(Please like the answer it will encourage me. Do comment if any correction required before disliking.)


Related Solutions

Use the data given in the table to answer the following questions. The data represents the...
Use the data given in the table to answer the following questions. The data represents the average number of miles that a salesperson travels in a day verses the number of sales made each month. Miles, x 24 32 75 41 76 107 32 46 112 Sales, y 76 58 190 112 141 235 24 147 188 (a) What is the value of the correlation coefficient for this set of data? Round to 3 decimal places. (b) What is the...
1. Use this data table for the bromination of acetone to answer the following questions; Experiment...
1. Use this data table for the bromination of acetone to answer the following questions; Experiment [CH3COCH3] (M) [Br2] (M) [H+] (M) Rate (M s-1) 1 0.3 0.05 0.05 0.000057 2 0.3 0.10 0.05 0.000057 3 0.3 0.05 0.10 0.000120 4 0.4 0.05 0.20 0.000310 5 0.4 0.05 0.05 0.000076 a) Determine the reaction order with respect to each of the three reactants and write the rate law. b) What is the value of the rate constant including proper units?
Use the following to answer Questions. The table includes summary of data concerning advertising expenditures and...
Use the following to answer Questions. The table includes summary of data concerning advertising expenditures and computer sales for ACME electronics. Ad Expenditures ($1000) Computer Sales ($1000) 2.5 6.1 3.8 4.9 3.1 5.9 2.1 6.8 What is the linear regression equation for the data? Y = 8.88 – 1.03x Y = 5.22 – 1.92x Y = 6.85 + 1.03x Y = 3.72 + 2.46x What is the standard error of the regression model? .2219 .3276 .7324 .9777 What is the...
Use the following data to answer the questions below:
Use the following data to answer the questions below:             Q                 VC             MC           AVC              1                 $10              ___            ___                                   2                16              ___            ___                       3                20              ___            ___                                   4                25              ___            ___              5                31              ___            ___              6                  38              ___            ___                  7                  46              ___            ___8                  55              ___            ___9                  65              ___            ___         a. Calculate the marginal cost and average variable cost for each level of production.b. How much would the firm produce if it could sell its product for...
Answer the following questions using the data given in the table. Use the T-Test Paired Two...
Answer the following questions using the data given in the table. Use the T-Test Paired Two Sample for Means to arrive at the solutions to the questions below. Use an alpha value of 0.01 Home Appraiser 1 Appraiser 2 A $235,000 $228,000 B $210,000 $205,000 C $231,000 $219,000 D $242,000 $240,000 E $205,000 $198,000 F $230,000 $223,000 G $231,000 $227,000 H $210,000 $215,000 I $225,000 $222,000 J $249,000 $245,000 K $199,000 $201,000 1 What is the value for the test...
The following questions use the table below on soybean oil. Answer the following questions about an...
The following questions use the table below on soybean oil. Answer the following questions about an end user needing to purchase soybean oil. One soybean oil contract is 60,000 pounds (lbs). Now Later Cash Soybean Meal Market $0.335/lb $0.346/lb Futures Soybean Meal Market $0.3000/lb $0.311/lb 1) Is the individual concerned about price increasing or decreasing? 2) What is the initial action in the futures market: buy or sell? 3) What is the cash price paid/received by the individual later? 4)...
Values in the table below are approximate. Use these to answer the following questions and to...
Values in the table below are approximate. Use these to answer the following questions and to compare health impact of the two diseases. R-naught Incubation period Contagious Period COVID-19 2.5 10 days 2-3 days before symptoms to 10 days after Rabies 1.5 Several months From symptoms to 10 days after symptoms Recall that R-naught is the average number of additional cases that directly result from a single person bringing it into a fully susceptible community. Below, compare in the impact...
Use the data in the table about Homer’s Donuts to answer the questions below: Number of...
Use the data in the table about Homer’s Donuts to answer the questions below: Number of workers Total Output Total Revenue Value of the marginal product of labor 0 0 1 40 2 70 3 90 4 100 5 105 6 107 7 105 a. Complete the table assuming a price of $1.00.    b. Assuming the price of donuts is $1.00, and the market wage is $8 an hour, what is the maximum number of workers Homer will hire?   __________________________...
Use the data in the table about Homer’s Donuts to answer the questions below: Number of...
Use the data in the table about Homer’s Donuts to answer the questions below: Number of workers Total Output (per hour) Total Revenue Value of the marginal product of labor (per hour) 0 0 1 20 40 2 35 30 3 45 20 4 50 10 5 54 8 6 56 4 7 53 -6 a. Complete the table assuming a price of $1.00.    b. Assuming the price of donuts is $1.00, and the market wage is $8 an hour,...
Use the data in the following table for the next seven questions. Note that "%∆" is...
Use the data in the following table for the next seven questions. Note that "%∆" is shorthand for "percentage change." If the answer is a percentage, please just enter the number. Thus, say an answer of yours is 3.5%, then below you would enter "3.5" (without the quotes) in the box below. Be careful not to include the percent symbol. Also, please use just one decimal place. year real GDP (trillions) nominal GDP (trillions) CPI %∆CPI from the previous year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT