The following table provides data for a project. Use the data to answer the following questions
Activity |
Immediate Predecessor |
Time Estimates (weeks) |
||||
Optimistic |
Most Likely |
Pessimistic |
Expected |
Variance |
||
A |
- |
6 |
7 |
14 |
||
B |
- |
8 |
10 |
12 |
||
C |
A |
2 |
3 |
4 |
||
D |
A |
6 |
7 |
8 |
||
E |
B,C |
5 |
5.5 |
9 |
||
F |
B,C |
5 |
7 |
9 |
||
G |
D,E |
4 |
6 |
8 |
||
H |
F |
2.5 |
3 |
3.5 |