Question

In: Accounting

Consider the project with the listed activities. Normal durations and costs, as well as crash durations...

Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).
                                Crash     Crash                                     Normal                 Normal

Activity                 Time      Cost                                       Time                      Cost

(1, 2)                      5              $41,000                                 8                              $29,000

(1, 3)                      2              $18,000                                 3                              $10,000

(2, 4)                      10           $50,000                                 12                           $46,000

(2, 5)                      4              $26,000                                 6                              $20,000

(3, 5)                      9              $18,000                                 11                           $15,000

(4, 6)                      4              $22,000                                 5                              $20,000

(5, 6)                      4              $13,000                                 4                              $13,000

(5, 7)                      8              $30,000                                 10                           $25,000

(6, 8)                      3              $15,000                                 5                              $10,000

(7, 8)                      4              $10,000                                 5                              $7,000

*Times are in weeks

(a) Assuming that all activities are completed according to their normal durations, how long will it take to complete the project?

(b) Suppose that you wanted to shorten the duration of the project by 3 weeks. Which activities would you shorten, and by how much? What additional cost would you incur by doing this?

Solutions

Expert Solution

The project network diagram for the given scenario is as follows:

The duration of the various paths are as follows:

Path A: 1 - 2 - 4 - 6 - 8 = 5 + 10 + 4 + 3 = 22 Weeks

Path B: 1 - 2 - 5 - 6 - 8 = 5 + 4 + 4 + 3 = 16 Weeks

Path C: 1 - 2 - 5 - 7 - 8 = 5 + 4 + 8 + 4 = 21 Weeks

Path D: 1 - 3 - 5 - 6 - 8 = 2 + 9 + 4 + 3 = 18 Weeks

Path E: 1 - 3 - 5 - 7 - 8 = 2 + 9 + 8 + 4 = 23 Weeks

The highest duration Path is 1 -- 3 -- 5 -- 7 -- 8. Therefore, it is the critical path.

(a) If all the activities are completed according to their normal durations, the project would get completed in 23 weeks.

(b) If the duration is to be shortened by 3 weeks:

The cost slope information for the activities are as follows:

In order to decrease the duration of the project, we need to first decrease the duration of the critical path.

The activity having least cost slope among the critical path activities is 3 -- 5. If we reduce 1 week by crashing Activity 3-5, we would incur additional cost of $1,500.

Then the project duration would become 22 Weeks.

With 22 weeks duration, we would have two critical paths and those are, Path A and Path E.

Now we need to crash the activities from each of the critical path.

Crashing activity 2-4 by 2 weeks would incur additional crashing cost of $4,000.

Crashing activity 3-5 by one week and activity 5-7 by one week would incur the additional crashing cost of $4,000 ($1,500 + $2,500)

Therefore, the activities which should be shortened are:

Activity 3-5 by 2 weeks;

Activity 5-7 by 1 week;

Activity 2-4 by 2 weeks.

Additional cost of crashing = $1,500 + $4,000 + $4,000 = $9,500


Related Solutions

4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal...
4). Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal condition are as follows: Activity Duration in Weeks Crew size AC 6 8 BC 6 7 BE 2 6 CD 3 2 CE 4 1 DF 7 4 EF 4 6 FG 5 10 Extra crew members can be used to expedite activities BC, CE, DF, and EF at a cost given below: Extra Crew Weeks Saved Crash cost per week 1 1 $100...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Listed below are the durations​ (in hours) of a simple random sample of all flights of...
Listed below are the durations​ (in hours) of a simple random sample of all flights of a space shuttle program. Find the​ range, variance, and standard deviation for the sample data. Is the lowest duration time​ unusual? Why or why​ not? 76    90    234    195    165    265    197    372    252    237    384    340    225    245    0
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations....
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations. Identify the critical path and list the slack times (if any) for the activities. Activity Immediate Predecessor Duration A - 3 B - 3 C - 4 D A, B 5 E B, C 4 F D, E 2 G E 3 H F, G 5  
#19: Lemons and car crashes using the listed lemon/crash data, find the best predicted crash fatality...
#19: Lemons and car crashes using the listed lemon/crash data, find the best predicted crash fatality rate for a year in which there are 500 metric tons of lemon imports. Is the predication worthwhile? Lemon Imports 230 265 358 480 530 Crash Fatality rate 15.9 15.7 15.4 15.3 14.9
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT