Given the following information, compute the early, late, and slack times for the project network.



Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?

image.png

Solutions

Expert Solution

Network Diagram is prepared using Handwritten Format, here, I have used forward and backward path Method,

Important Formula:

Early start of an activity = Highest Early finish time among all predecessor activities

Late finish of an activity = Lowest Late start time among all successor activities,

Slack = Late start - Early Start = late Finish - Early finish

Early finish = Early start + Duration

Late start = Late finish - Duration

From the below network diagram, critical path is Start - A-B-D-E-F-G-H-J-End,

as activities on that path have zero slack time, project needs 38 unit time to complete,

Early finish of predecessor activity+ Lag time = Early start of an activity

Late finish of an Activity = Late start of an successor activity - Lag time,

ES,EF, LS, LF and Slack data for each activity are shown in the below network diagram,


Related Solutions

Given the following information, you are to determine the following Project network. Early, late and slack...
Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 5 B A 8 C A 15 D A 10 E A 10 F B 10 G C, D 12 H E, 15 I G, H 7 J F,G,I 10 K J 12
Given the following information, estimate the cash flows of this project and then compute the NPV...
Given the following information, estimate the cash flows of this project and then compute the NPV of this project. Estimated Sales: 50,000 units per year for each of the next 3 years Estimate Sale Price: $1,050 per unit Variable Cost: $1,000 per unit Fixed Costs: $1,500,000 per year Initial Investment in Plant and Machinery: $1,500,000 to be depreciated to a salvage value of $0 over the next three years. We sell the machine at $45000 in the market at the...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 6 8 10 B A 1 2 4 C A 9 12 15 D A 3 4 5 E B 4 6 7 F B 14 16 22 G C, D 2 3 4 H E, G 1 2 3 I G 6 8 9 J H, I 4 6 8 K F, H, J 1 2 5 a. Draw the...
NETWORK SYSTEM MANAGEMENT. Given the following attributes in a project management:  Project scope & feasibility...
NETWORK SYSTEM MANAGEMENT. Given the following attributes in a project management:  Project scope & feasibility  Documentation  Project planning  Testing and piloting  Risk minimisation Discuss briefly each of them and on how would you use them as the IT manager for the company. Provide a details information support your discussion. Remarks: Total 50 Marks for this questions.
1. Compute the NPV of a project with the following information. The IRR is 9%. The...
1. Compute the NPV of a project with the following information. The IRR is 9%. The project life is 3 years. The initial cost is $19,000. In years 1 and 2 the cash inflows are $4,500 and $5,500, respectively. Cash flow in year 3 is missing. WACC is 12%.
From the information given below, compute the time in days for the following notes: Date of...
From the information given below, compute the time in days for the following notes: Date of Note Due Date Time in Days 1. June 28, 2010 August 10, 2010 days 2. March 5, 2010 August 12, 2010 days 3. April 20, 2010 July 17, 2010 days 4. January 12, 2010 May 15, 2010 days 5. December 17, 2010 February 2, 2011 days From the information given below, determine the due date for the following notes:        Date of Note       Time...
In the following Table you are given information on Real GDP and Nominal GDP. Compute the...
In the following Table you are given information on Real GDP and Nominal GDP. Compute the percentage change in Nominal GDP from 1970 to 1980 (15 points) and the percentage change in Real GDP (15 points) from 1970 to 1980. Year Nominal GDP (In Current Prices) Real GDP (Base Year 2000 Prices) 1970 4,000 2,000 1980 6,000 4,500 Where do you attribute the difference between the two percentage changes?
Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given...
Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Cost Driver Maintenance $20,000 $10,000 Machine hours Materials handling 30,000 15,000 Material moves Machine setups 70,000 5,000 Machine setups Inspections - 25,000 Inspection hours $120,000 $55,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours 10,000 5,000 Material moves 3,000 1,500 Machine setups 700 50 Inspection hours - 1,000 It...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT