Question

In: Operations Management

1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days.


Supplemental assignment for MGMT8300: Network Diagram and the Critical Path 

1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days. image.png

2. What is the critical path? 

3. How long will it take to complete the project if everything goes according to plan? 

4. Choose an activity that is not on the critical path. How many days longer should it take in order for the critical path to be different from the original critical path that you found in step 2? 

Solutions

Expert Solution

1.

2.

Project paths Duration
A-D-G-J-K 15
A-B-E-I-J-K 14
A-B-E-H-K 10
A-C-F-I-J-K 16 (Max)
A-C-F-H-K 12

The path A-C-F-I-J-K, being the longest path, is the critical path.

3.

If everything goes as per plan, the project will finish 16 days.

4.

Let us choose 'B'.

If the duration of 'B' is 5 days, the duration of the path A-B-E-I-J-K will be 17 days and this will be the critical path in that case.

So, B's duration has to increase by 5 - 2 = 3 days in this case.

If the duration of B becomes 4 days (i.e. an increase of 2 days from what it is now), there will be two critical paths - A-C-F-I-J-K and A-B-E-I-J-K both having duration = 16 days.


Related Solutions

Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all...
Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity L....
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2....
Given the accompanying network diagram, with times shown in days. Use Table B1 and Table B2. a. Determine the expected duration of the project. (Round intermediate calculations to 2 decimal places and final answer to 1 decimal place.) Expected Duration             b. Compute the probability that the project will take at least 18 days. (Round intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability             Chuck’s Custom Boats (CCB) builds luxury yachts to...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
This question is based on our three-node network where all resistances are equal. Generators are located...
This question is based on our three-node network where all resistances are equal. Generators are located at nodes 1 and 2, while the customer is located at node 3. Power flows through the network are: F(1,3) = 44 MW F(2,3) = 56 MW F(1,2) = -12 MW (i.e., 12 MW from node 2 to node 1) The transmission limit on Line (1,2) is 10 MW in either direction, so the line is overloaded by 2 MW. Assume that lines (2,3)...
Problem 6-23 (Algorithmic) Find the shortest route from node 1 to node 7 in the network...
Problem 6-23 (Algorithmic) Find the shortest route from node 1 to node 7 in the network shown. If the constant is "1" it must be entered in the box. If your answer is zero enter "0". For negative values enter "minus" sign (-). Min x12 + x13 + x14 + x23 + x25 + x32 + x35 + x46 + x52 + x53 + x56 + x57 + x65 + x67 s.t. Flow Out Flow In Node 1 x12 +...
Given the following binary relations R on two sets, for each relation: Draw the arrow diagram...
Given the following binary relations R on two sets, for each relation: Draw the arrow diagram of R. Is R a function, and why? If R is a function, determine if it is injective or surjective. Is the function bijective? Justify your answers. R = {(a, 3), (c, 1)} on domain {a, b, c} and codomain {1, 2, 3} R = {(1, a), (3, c), (2, b)} on domain {1, 2, 3} and codomain {a, b, c} R = {(a,...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation;...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation; simple answers alone will not account for full marks) • Activity 1 can start immediately and has an estimated duration of three weeks. • Activity 2 can start after activity 1 is completed and has an estimated duration of three weeks. • Activity 3 can start after activity 1 is completed and has an estimated duration of six weeks. • Activity 4 can start...
Ex1) Develop an activity diagram and use case diagram based on the following narrative. The purpose...
Ex1) Develop an activity diagram and use case diagram based on the following narrative. The purpose of the Open Access Insurance System is to provide automotive insurance to car owners. Initially, prospective customers fill out an insurance application, which provides information about the customer and his or her vehicles. This information is sent to an agent, who sends it to various insurance companies to get quotes for insurance. When the responses return, the agent then determines the best policy for...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT