Question

In: Operations Management

Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...

Activity

Optimistic Time Estimate

(weeks)

Most Likely Time Estimates (weeks)

Pessimistic Time Estimates (weeks)

Immediate Predecessor(s)

A

3

6

9

none

B

3

5

7

A

C

4

7

12

A

D

4

8

10

B

E

5

10

16

C

F

3

4

5

D, E

G

3

6

8

D, E

H

5

6

10

F

I

5

8

11

G

J

3

3

3

H, I

A.)Using the information given, construct a network diagram using AON notation.

B.) Using the information given, calculate the expected time for each of the project activities.

C.) Using the information given, calculate the variance for each of the project activities.

D.) Using your results from Problems B and C, Calculate the completion time for this project.

E.) Identify the activities included on the critical path of this project.

F.) Using your results from Problem D and E, Calculate the probability that the project will be completed in 38 weeks.

G.) Calculate the probability that the project will be completed in 42 weeks.

Solutions

Expert Solution

A.)Using the information given, construct a network diagram using AON notation.

B.) Using the information given, calculate the expected time for each of the project activities.

Expected time =( Optimistic Time + 4 (most likely Time) + the pessimistic time) / 6

EG for A

=(3+4(6)+9)/6 =6

Activity

Optimistic Time Estimate

Most Likely Time Estimates (weeks)

Pessimistic Time Estimates (weeks)

Expected time=(Optimistic Time + 4 (most likely Time) + the pessimistic time) / 6

(weeks)

A

3

6

9

6.00

B

3

5

7

5.00

C

4

7

12

7.33

D

4

8

10

7.67

E

5

10

16

10.17

F

3

4

5

4.00

G

3

6

8

5.83

H

5

6

10

6.50

I

5

8

11

8.00

J

3

3

3

3.00

C.) Using the information given, calculate the variance for each of the project activities.

Variance for each activity =(( Pessimistic time – optimistic time)/ 6)2

EG for A

=((9-3)/6) 2=1

Activity

Optimistic Time Estimate

Most Likely Time Estimates (weeks)

Pessimistic Time Estimates (weeks)

Variance for each activity=((p-o)/6)^2

(weeks)

A

3

6

9

1.00

B

3

5

7

0.44

C

4

7

12

1.78

D

4

8

10

1.00

E

5

10

16

3.36

F

3

4

5

0.11

G

3

6

8

0.69

H

5

6

10

0.69

I

5

8

11

1.00

J

3

3

3

0.00

D.) Using your results from Problems B and C, Calculate the completion time for this project.

Expected project completion time is determined by the critical path –

Critical Path = longest connected path in the network

PATHS                                  

ABDFHJ-                6+5+7.67+4+6.5+3 =                           32.17 weeks

ABDGIJ -               6+5+7.67+5.83+8+3=                          35.5 weeks

A CEFHJ-                6+7.33+10.17+4+6.5+5=                      39 weeks

ACEGIJ   -               6+7.33+10.17+5.83+8+3=                    40.33 weeks

Critical Path = longest connected path in the network = ACEGIJ =40.33 weeks

Expected completion time for the project, E(t)= 40.33

E.) Identify the activities included on the critical path of this project.

ACEGIJ

F.) Using your results from Problem D and E, Calculate the probability that the project will be completed in 38 weeks.

D=38 weeks

Expected completion time for the project, E(t)= 40.33

Variance of the project

= sum of the variances of the activities in critical path

=

= 1+1.78+3.36+0.69+1+0

=7.83

Z score

=( specified time – path expected completion) / path standard deviation

= (38-40.33)/ ?(7.83)

=   -0.83

Using a standard distribution , we find that a Z value of   - 0.87 yields a probability of 0.2033, which means that probability of completing the project in 38 weeks is 20.33%

G.) Calculate the probability that the project will be completed in 42 weeks.

D=42 weeks

E(t)= 40.33

Variance of the project

= sum of the variances of the activities in critical path

= 1+1.78+3.36+0.69+1+0

=7.83

Z= (42-40.33)/ ?(7.83) =   0.60

Using a standard distribution, we find that a Z value of 0.60 yields a probability of 0.7257, which means that probability completing the project in 42 weeks 72.57%    


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT