Question

In: Operations Management

1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...

1) Consider the network corresponding to the following information.

Activity

Immediate

Predecessor(s)

Time

(Weeks)

A

---

3

B

---

4

C

A

6

D

B

9

E

B

6

F

C, D

6

G

D, E

8

H

G, F

9

  1. Draw the network corresponding to the above information.
  2. Using a table format, identify the critical path.
  3. What is the project completion time?

Solutions

Expert Solution

2. Critical path: It is the longest distance between the start and finish of the project.

The available paths are:

ACFH = 24

BDFH = 28

BDGH = 30

BEGH = 27

Here, the critical path is BDGH as it has longest time duration.

Hence, ES and EF are calculated in the forward pass fashion from this path.

Next, BDFH path is calculated. Then, BEGH and ACHF are calculated respectively.

Same sequence is followed for calculating Backward pass.

EF denotes the Early Finish.

LS denotes the Latest Start.

LF denotes the Latest finish.

ES is the time of initiation of the activity.

EF = ES + Activity time

LF is the latest finish of the activity.

LS = LF – Activity time

Slack = LS – ES or LF – EF (Both the formulas lead to same result)

ES for the starting activity will be Zero and for other activities the EF value of the previous activity will be the ES for current activity.

Activity

Duration

ES

EF

LS

LF

Slack

A

3

0

3

6

9

6

B

4

0

4

0

4

0

C

6

3

9

9

15

6

D

9

4

13

4

13

0

E

6

4

10

7

13

3

F

6

13

19

15

21

2

G

8

13

21

13

21

0

H

9

21

30

21

30

0

The slack of the activity path BDGH is 0. Hence it can be considered as critical path.

3. Hence, the project completion time is 30 weeks as BDGH is the critical path.

1. The below is the network diagram.


Related Solutions

Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal...
The relevant project data are given as follows. Activity Predecessor(s) Normal time (weeks) Crash time Normal cost Crash cost Possible number of weeks to crash Cost/week to expedite A -- 7 6 $7,000 $8,000 B A 2 1 5,000 7,000 C A 4 3 9,000 10,200 D B,C 5 4 3,000 4,500 E D 2 1 2,000 3,000 F D 4 2 4,000 7,000 G E,F 5 4 5,000 8,000 a)    Draw the AOA (Activity-On-Arc) diagram as shown in...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 -...
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4 3 5 5 3 4 The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT