Question

In: Operations Management

One of the tasks that needed to be completed after activity sequencing, is allotting duration times...

One of the tasks that needed to be completed after activity sequencing, is allotting duration times for each activity. Name and discuss three options for calculating activity duration.

Solutions

Expert Solution

Answer:

Sequencing: Sequencing is the process in which, all the operation or machines or work stations are arranged in their order of execution. The operation which start the process is placed in the start of the sequence and then followed by all other operations which follows one by one and ends with the last operation to be performed.

Activity Duration: Activity duration is defined as the time taken by the activity to be performed within that time duration. Thus the lead time of the activity is known as the activity duration.

This can be calculated by below three approaches as below.

  • Expert Judgment Approach: The easiest way for calculating the activity duration is by having the expert judgment. The expert judgment will mention the activity duration by his expertise of past experience in that field. This is the simplest approach of activity duration assignment.
  • Historical Data Average Approach: This is more realistic approach, in which the historical data are used and their average is used as time duration for each activity. This is a data driven approach in which old or historical data are used for calculating the time duration for all the activities.
  • Group Decision-Making Approach: This is another approach in which the a group is formed and based on the knowledge level and expertise of the group, the time duration is assigned to each activity. This is based on experience, biasness and skill sets of the group involved in the time duration calculation exercise. This is a group perception based approach.
  • Time study Approach: This is the approach in which actual time is calculated for the activity. So based on actual time calculation for the study, the time is assigned for the activity. This approach is used in the machine production environment. But this is not suitable for the project management approach.
  • Estimation Approaches: Various estimating approaches can be used for the time duration calculation for the project operations. Analogues estimating, parametric estimation and three point estimation are some of the key techniques used for activity duration estimation.

Related Solutions

Assume that for this project to be completed, five independent tasks must be completed. These tasks...
Assume that for this project to be completed, five independent tasks must be completed. These tasks are proceeding in parallel by five different subcontractors. To keep it simple, let's assume that each task takes between 1 and 5 months to complete (uniformly distributed, i.e. equally likely to take any amount of time between 1 and 5 months). So, the mean time to complete each task is 3 months and the probability of any given task taking 3 months or longer...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
Duration of a ZCB repayable after seven years will be: Select one: a. More than seven...
Duration of a ZCB repayable after seven years will be: Select one: a. More than seven years b. 3.5 years c. Less than seven years d. Seven years e. None of these
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
8. if the project duration needs to be reduced then a. the activity with the lost...
8. if the project duration needs to be reduced then a. the activity with the lost cost should be selected b. activity which is currently undergoing should be selected c. activity with the highest cost should be selected d. activity on the critical path should be selected . 9. it does not make any sense to crash if a. if there is no critical activity left b. project crashing cost is equal or more than saving c. project is more...
how can i make Activity duration estimates?
how can i make Activity duration estimates?
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...