Question

In: Operations Management

The duration and resource usage for each activity are showed in the table below. Activity Predecessor...

The duration and resource usage for each activity are showed in the table below.

Activity

Predecessor

Total Processing Time (days)

# of painters required/day

A

---

0.5

1

B

---

1

1

C

A,B

1

1

D

C

1

1

Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day 1).

Answer Options:

In the morning of Day 2

The whole day of Day 1

In the morning of Day 1

The whole day of Day 2

Solutions

Expert Solution

The Activity diagram will be:

Computation of earliest starting and finishing times is aided by two simple rules:
1. The earliest finish time for any activity is equal to its earliest start time plus its expected
duration, t:
EF = ES + t
2. ES for activities at nodes with one entering arrow is equal to EF of the entering arrow. ES
for activities leaving nodes with multiple entering arrows is equal to the largest EF of the
entering arrow.
Computation of the latest starting and finishing times is aided by the use of two rules:
1. The latest starting time for each activity is equal to its latest finishing time minus its
expected duration:
LS = LF - t
2. For nodes with one leaving arrow, LF for arrows entering that node equals the LS of the
leaving arrow. For nodes with multiple leaving arrows, LF for arrows entering that node
equals the smallest LS of leaving arrows.
Finding ES and EF times involves a forward pass through the network; finding LS and LF
times involves a backward pass through the network. Hence, we must begin with the EF of the
last activity and use that time as the LF for the last activity. Then we obtain the LS for the last
activity by subtracting its expected duration from its LF
Slack = LS-ES = LF-EF
Activities for which Slack = 0 are in critical path
Expected time ES EF LS LF Slack On Critical Path
A 1 0                 0.50                     0.50                             1.00              0.50 No

B

1 0                 1.00                         -                               1.00                   -   Yes
C 1 1                 2.00                     1.00                             2.00                   -   Yes
D 1 2                 3.00                     2.00                             3.00                   -   Yes

The printer allocation will begin with either A or B. However, A has Slack of 0.5 and B has Slack of 0. So, first, the allocation will be to B. Also, the processing time is 1 day. So, B will begin on Day 1 and continue for whole day

Ans - The whole day of Day 1

If you liked my answer, please give an Up-vote. This will be quite encouraging for me. Thank you!


Related Solutions

The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 1 1 B --- 1 1 C A,B 0.5 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". How much slack time (in days) does acitivity C have after leveling recources?
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost...
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash by 1 day Max Days to Crash A 5 - $       300 1 B 3 - $       100 1 C 4 A $       100 1 D 3 A $       200 2 E 4 B $       400 3 F 2 D, E $       500 2 G 4 E $       300 3 H 3 C $       100 2 1. What is the critical path of this project? 2. What is the duration...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A...
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A --- 5 B --- 5 C --- 5 D A, B 4 E B 3 F C 8 G D, E 6 What is the minimum number of activities that have to be delayed for the project to get delayed? 1 2 3 4 5 None of the above (What is your answer?) What is the minimum number of non-critical activities that have to...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8 - B 5 7 9 - C 2 4 6 - D 1 2 3 A E 1 4 7 C F 3 6 9 B,D,E G 1 5 9 F H 1 2 3 F I 2 5 8 G,H Draw an AON network based on the given table Determine the expected time for each activity Calculate the ES, EF, LS, LF for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT