Question

In: Operations Management

8. if the project duration needs to be reduced then a. the activity with the lost...

8. if the project duration needs to be reduced then

a. the activity with the lost cost should be selected

b. activity which is currently undergoing should be selected

c. activity with the highest cost should be selected

d. activity on the critical path should be selected

.

9. it does not make any sense to crash if

a. if there is no critical activity left

b. project crashing cost is equal or more than saving

c. project is more than 75% compelet

d. project crashing cost can not be calculated

.

10. forecast errors can not be attributed to

a. sudden change in trend

b. past sales data

c. random variation

d. change in business environment

Solutions

Expert Solution

Answer to question 8 :

A project has multiple sets of paths consisting of various activities. Out of these paths, one or more than one is/are critical path(s). Critical paths are those which takes maximum time to execute and complete. Naturally. Project duration becomes equivalent to the duration of the critical path. All other non-critical paths will have durations lesser than durations of critical path. Therefore, if a project’s duration needs to be reduced, one needs to target reducing the durations of critical paths. It will be a futile effort to reduce the duration of a project by reducing durations of non-critical paths without paying attention to the need for reduction of durations of critical paths. Therefore the correct answer would be “ d. activity on the critical path should be selected”

IF THE PROJECT DURATION NEEDS TO BE REDUCED THEN ACTIVITY ON THE CRITICAL PATH SHOULD
BE SELECTED.

Answer to question 9 :

The main purpose of crashing is to fruitfully reduce project duration. It requires the allocation of resources that cost money. However such allocation of resources reduces the duration of a specific activity which in turn helps to reduce the duration of the project. Reduced duration of projects brings advantages to its stakeholders financially as well as qualitatively. It is always a priority to first target activities on the critical path for the purpose of crashing.

However underlying principle should be that additional resource costs committed for the crashing of activities should be compensated by bigger gain achieved through reduction of project duration. Therefore correct answer should be “b. project crashing cost is equal to or more than saving “

IT DOES NOT MAKE ANY SENSE TO CRASH IF PROJECT CRASHING COST IS EQUAL TO OR MORE THAN SAVING


Related Solutions

QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ Options: 0 1 2 3
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 1 B --- 1 1 C A,B 1 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 1 1 B --- 1 1 C A,B 0.5 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". How much slack time (in days) does acitivity C have after leveling recources?
how can i make Activity duration estimates?
how can i make Activity duration estimates?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT