Question

In: Operations Management

Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...

Times (days)

Activity

Optimistic

Most Likely

Pessimistic

Preceding Tasks

1

8

10

13

-

2

5

6

8

-

3

13

15

21

2

4

10

12

14

1,3

5

11

20

30

4

6

4

5

8

5

7

2

3

4

5

8

4

6

10

7

9

2

3

4

8,6

  1. Draw the AON Network Diagram
  2. Compute the expected activity time
  3. Using the expected activity times, compute the early start, early finish, late start, late finish, and total float for each activity.
  4. Compute the probability of completing the critical path in 69 days.

Solutions

Expert Solution

(a)

(b)

Activity Preceding Tasks a m b te = (a + 4m + b) / 6 Variance = (b - a)2/36
1 - 8 10 13 10.167 0.694
2 - 5 6 8 6.167 0.250
3 2 13 15 21 15.667 1.778
4 1,3 10 12 14 12.000 0.444
5 4 11 20 30 20.167 10.028
6 5 4 5 8 5.333 0.444
7 5 2 3 4 3.000 0.111
8 7 4 6 10 6.333 1.000
9 8,6 2 3 4 3.000 0.111

(c)

Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) time for each activity can be computed using the following rules.

Activity Preceding Tasks te = (a + 4m + b) / 6 ES EF LS LF Total float = LF - EF
1 - 10.167 0.000 10.167 11.667 21.833 11.667
2 - 6.167 0.000 6.167 0.000 6.167 0.000
3 2 15.667 6.167 21.833 6.167 21.833 0.000
4 1,3 12.000 21.833 33.833 21.833 33.833 0.000
5 4 20.167 33.833 54.000 33.833 54.000 0.000
6 5 5.333 54.000 59.333 58.000 63.333 4.000
7 5 3.000 54.000 57.000 54.000 57.000 0.000
8 7 6.333 57.000 63.333 57.000 63.333 0.000
9 8,6 3.000 63.333 66.333 63.333 66.333 0.000

(d)

The critical path consists of activities with zero slack, so the critical path is 2-3-4-5-7-8-9.

Activity Preceding Tasks te = (a + 4m + b) / 6 Variance = (b - a)^2/36
2 - 6.167 0.250
3 2 15.667 1.778
4 1,3 12.000 0.444
5 4 20.167 10.028
7 5 3.000 0.111
8 7 6.333 1.000
9 8,6 3.000 0.111
Total 66.333 13.722

So, project mean duration = 66.333
stdev = sqrt(13.722) = 3.704

So,

Prob{duration < 69} = NORM.DIST(69, 66.33, 3.704,1) = 0.764


Related Solutions

Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 6 8 10 B A 1 2 4 C A 9 12 15 D A 3 4 5 E B 4 6 7 F B 14 16 22 G C, D 2 3 4 H E, G 1 2 3 I G 6 8 9 J H, I 4 6 8 K F, H, J 1 2 5 a. Draw the...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT