Question

In: Operations Management

The duration and resource usage for each activity are showed in the table below. Activity Predecessor...

The duration and resource usage for each activity are showed in the table below.

Activity

Predecessor

Total Processing Time (days)

# of painters required/day

A

---

1

1

B

---

1

1

C

A,B

0.5

1

D

C

1

1

Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". How much slack time (in days) does acitivity C have after leveling recources?

Solutions

Expert Solution

First, I have prepared Network Diagram for given table and activities:

Network diagram is prepared using forward and backward path method

Based on the Network diagram, we see that we have two critical path, these are Start - A-C-D- End, Start-B-C-D-End, project will take at least 2.5 days to complete.

Based on the network diagram, i have prepared Gantt chart, as shown below:

Gantt chart before Resource leveling:

Activity Duration Resources 0.5 1 1.5 2 2.5
A 1 1 1 1
B 1 1 1 1
C 0.5 1 1 1 1
D 1 1
Total Resources 2 2 1 1 1
Allowable resources 1 1 1 1 1

Gantt chart after Resource leveling:

the rule "Delay the activity with the most positive slack first". but here, all activities have zero slack or total float, here, I have delayed activity B by 1 day.

After Resource levelling
Activity Duration Resources 0.5 1 1.5 2 2.5 3 3.5
A 1 1 1 1
B 1 1 1 1
C 0.5 1 1
D 1 1 1 1
Total Resources 1 1 1 1 1 1 1
Allowable resources 1 1 1 1 1 1 1

now project will take at least 3.5 days to complete.

Here, we have got only one path and all activities on this path would be critical path activities, project will take at least 3.5 days to complete.

After Resource leveling,

Total slack or float for activity C =Late start - Earliest start=Late finish - earliest finish = 2-2=2.5-2.5= Zero


Related Solutions

The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 1 B --- 1 1 C A,B 1 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day...
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost...
question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash by 1 day Max Days to Crash A 5 - $       300 1 B 3 - $       100 1 C 4 A $       100 1 D 3 A $       200 2 E 4 B $       400 3 F 2 D, E $       500 2 G 4 E $       300 3 H 3 C $       100 2 1. What is the critical path of this project? 2. What is the duration...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A...
Assume a project information is given in the table below: Activity Immediate Processor Duration (Days) A --- 5 B --- 5 C --- 5 D A, B 4 E B 3 F C 8 G D, E 6 What is the minimum number of activities that have to be delayed for the project to get delayed? 1 2 3 4 5 None of the above (What is your answer?) What is the minimum number of non-critical activities that have to...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8 - B 5 7 9 - C 2 4 6 - D 1 2 3 A E 1 4 7 C F 3 6 9 B,D,E G 1 5 9 F H 1 2 3 F I 2 5 8 G,H Draw an AON network based on the given table Determine the expected time for each activity Calculate the ES, EF, LS, LF for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT