Question

In: Operations Management

how can i make Activity duration estimates?

how can i make Activity duration estimates?

Solutions

Expert Solution

Acitivity duration estimates can be done through 5 ways

1.Analogous activity duration estimates

In this type we estimate the project based on the estimation of a similar past project. So we get an idea of the estimate. This gives entire duration estimate. We can get this information through operations management office or through manager. This saves time and cost. If we have less time to estimate the entire project we can use this sort of estimation. But this is not so accurate.

2. Parametric estimating

This is more accurate in nature. it is based on the calculations of historical data. If project is based on the same performed in the past this technique can be used.

3.Three point estimating

This is base don the assignment of resources, risk and uncertainity involved. This gives both best and worst scenarios and help in decision making. But this is cost effective. a lot of planning is required for it. This is done through PERT .ie. Program evaluation & Review Technique.

It includes three types of duration:

Most likely(M)

Optimistic(O)

Pessimistic(P)

M is based on resouces assigned to a particular project

O is based on the best scenario based analysis

P is based on worst scenario that can happen

The formula to derive the expected duration is

TE= (O+4M+P) / 6

TE is expected time

O is optimistic duration

P is pessimistic duration

M is most likely duration

4.Heuristic estimating

This is also termed as rule of thumb. This gives a roughly idea about this phase can take around 35% of the project. This is mainly based on experience. So experts generally talk about it.

5. Reserve analysis

This is a sort of contingency reserve in which we derive contingency reserve percentage to every schedule of the activity based on the past allocation of funds in the previous project.


Related Solutions

how can i establish workload and activity scheduling as a pm?
how can i establish workload and activity scheduling as a pm?
How's a bond's duration determined? How can a bond's duration be useful in managing a bond...
How's a bond's duration determined? How can a bond's duration be useful in managing a bond portfolio? What are the various features of a typical corporate bond?
How can I make an outline that describes to parents of adolescence how logic and decision...
How can I make an outline that describes to parents of adolescence how logic and decision making developments (considering "informal reasoning")? I need to use this outline as a format to explain behavioral manifestations of decision making.
How can I make an outline to describe to parent of adolescence how logic and decision...
How can I make an outline to describe to parent of adolescence how logic and decision making developments?I want to use this outline as a format to explain behavioral manifestations of decision making. I think it should include "informal reasoning". Thanks.
How can I make a problem like this simpler? and what equation do I use for...
How can I make a problem like this simpler? and what equation do I use for part D? Thanks! A researcher wonders if mental simulation will help one more successfully achieve one’s goals. To test this idea, the researcher recruited six students from a general psychology class, several weeks before their first midterm. After their first midterm, the researcher got the students’ scores on this test from their professor. Several weeks later, each of the students was brought into the...
Which of the following is true about duration and modified duration? I. The Macaulay duration calculates...
Which of the following is true about duration and modified duration? I. The Macaulay duration calculates the weighted average time before a bondholder would receive the bond's cash flows. II. Modified duration measures price sensitivity of a bond to changes in YTM by adjusting duration with a factor based on current yield. III. The value of duration and modified duration are usually very close, but duration is almost always a larger number.A.Duration is important to banks when they try to...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The formula is: Te = (o + 4m + p) / 6 Calculate duration estimates for...
The formula is: Te = (o + 4m + p) / 6 Calculate duration estimates for the following situation: The operations manager was in the process of upgrading the IT network and preparing estimates from the technology installers in regards to how long the existing network would be down during the upgrade. The technologists believed that it could be done within 8 days if everything went according to plan. There is the possibility it could take up to 16 days...
8. if the project duration needs to be reduced then a. the activity with the lost...
8. if the project duration needs to be reduced then a. the activity with the lost cost should be selected b. activity which is currently undergoing should be selected c. activity with the highest cost should be selected d. activity on the critical path should be selected . 9. it does not make any sense to crash if a. if there is no critical activity left b. project crashing cost is equal or more than saving c. project is more...
As a challenge question i was asked to make a program that can make a newly...
As a challenge question i was asked to make a program that can make a newly made Directory that has the name input from the user. I am to create a program that can make a txt file in the newly created directory. I am doing this in windows and this is what i got. #include <windows.h> #include <string> #include <iostream> #include <string.h> #include <fstream> #include <TlHelp32.h> using namespace std; int main() { string Text = "Test string"; ofstream file;...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT