Question

In: Operations Management

Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...

Activity Predecessor Activity Duration in Weeks
A ---- 3
B A 5
C A 7
D B 10
E C 5
F D, E 4

Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help).

I would really appreciate excel screenshots!

Solutions

Expert Solution

Create network diagram as follows:

List the alternative paths in the network and their respective length.

Length of each path is equal to the sum of times of activities on that path.

Path Length
A-B-D-F 22
A-C-E-F 19

The longest and hence critical path is: A-B-D-F

Date to finish the project = 22 weeks

Gantt chart is following:


Related Solutions

Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
Find the value of a : b : c : d, if a : b = 2 : 3, b : c = 4 : 5 and c : d = 6 : 7.
Find the value of a : b : c : d, if a : b = 2 : 3, b : c = 4 : 5 and c : d = 6 : 7.
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4 5 D 6 A,B 1 E 2 A,B,C 6 F 2 B,C 3 G 5 F 4 H 8 E,F 2 I 3 G 7 J 5 H,I 3 K 6 J 4 L 8 I 3 Calculate a lower bound for the number of workers required to complete the project in 26 days. [2 ????] Use the precedence table to draw an activity-on-arc...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT