| Activity | Predecessor Activity | Duration in Weeks | 
| A | ---- | 3 | 
| B | A | 5 | 
| C | A | 7 | 
| D | B | 10 | 
| E | C | 5 | 
| F | D, E | 4 | 
Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help).
I would really appreciate excel screenshots!
Create network diagram as follows:

List the alternative paths in the network and their respective length.
Length of each path is equal to the sum of times of activities on that path.
| Path | Length | 
| A-B-D-F | 22 | 
| A-C-E-F | 19 | 
The longest and hence critical path is: A-B-D-F
Date to finish the project = 22 weeks

Gantt chart is following: