Question

In: Operations Management

Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...

Consider the following precedence chart:

ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days)
A - 5 10 15
B - 10 12 14
C - 10 10 10
D B,C 2 4 6
E A 4 8 12
F A 4 8 12
G D,E 10 12 14
I F 4 8 12
J G 2 4 6


The total slack for activity F is __________

a.

8

b.

4

c.

2

d.

0

Solutions

Expert Solution

Solution:

From the given information, network diagram can be drawn as below:

The estimated expected time of each activity is calculated as;

Expected time, T = (a + 4m + b) / 6

where,

a = Optimistic time

m = Most likely time

b = Pessimistic time

Expected time of Activity A = [5 + (4 x 10) + 15) / 6 = 10

Expected time of Activity B = [10 + (4 x 12) + 14) / 6 = 12

Expected time of Activity C = [10 + (4 x 10) + 10) / 6 = 10

Expected time of Activity D = [2 + (4 x 4) + 6) / 6 = 4

Expected time of Activity E = [4 + (4 x 8) + 12) / 6 = 8

Expected time of Activity F = [4 + (4 x 8) + 12) / 6 = 8

Expected time of Activity G = [10 + (4 x 12) + 14) / 6 = 12

Expected time of Activity I = [4 + (4 x 8) + 12) / 6 = 8

Expected time of Activity J = [2 + (4 x 4) + 6) / 6 = 4

From the network diagram, the values of ES, EF, LS, LF can be computed as below:

ES = Early Start

EF = Early Finish

LS = Late Start

LF = Late Finish

From the above diagram,

ES for activity F = 10

EF for activity F = 18

LS for activity F = 18

LF for activity F = 26

Slack is calculated as;

Slack = (LS - ES) or (LF -EF)

Slack = 18 - 10

Slack = 8

The total slack for activity F = 8

Answer: Option (a) - 8


Related Solutions

Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10...
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
1.The following time estimates are given for an activity: optimistic time = 16 days, most likely...
1.The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 40 days. What is the variance of this activity? Group of answer choices A. 9 B. 16 C. 20 D. 24 E. None of these answers are correct 2.The expected waiting time in line is equal to the expected number of customers in line divided by the arrival rate Group of answer choices True False 3....
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none B 2 5 9 A C 4 6 12 A D 5 6 10 B E 6 10 17 C F 3 4 6 D,E G 3 6 10 D,E H 5 7 10 F I 5 8 11 G J 3 3 3 H,I (a) Calculate the expected completion time for this project. (Round...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
1. The following time estimates are given for an activity: optimistic time = 16 days, most...
1. The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38 days. What is the expected time to complete this activity? Group of answer choices A. 16 B. 24 C. 38 D. 25 E. None of these answers are correct 2. The project duration is equal to the sum of the durations of all activities in a network. Group of answer choices True False 3.The...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
Given the following project: Activity Predecessor Optimistic (day) Most Likely (day) Pessimistic (day) Start A, B,...
Given the following project: Activity Predecessor Optimistic (day) Most Likely (day) Pessimistic (day) Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 Identify the critical path of the project using activity expected time. What is the probability that the critical path will be completed in 205 days.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT