Question

In: Operations Management

The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...

The following information is provided about a training and development project.

Activity

Duration

(weeks)

Preceding Activities

A

3

None

B

5

None

C

14

A

D

5

A

E

4

B

F

7

B

G

8

D, E

H

5

G, F

          

(a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path.

[12 marks]

(b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks]

(c)       From which activity would you suggest transferring resources, and to what activity, so that the original target training date may be maintained?[6 marks]

[Total 25 marks]

sir if you can draw the diagrams on a paper since its easy to understand . thank you

Solutions

Expert Solution

PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU!!!

(a)

(b)

(c)

The project duration has increased from 22 weeks to 23 weeks, which is an increase of 1 week from the original duration. In order to maintain the original target training date, additional resources must be transferred to activities of the critical path. So, additional resources need to be transferred to activity D, G or H.

PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU!!!


Related Solutions

Q3. The following information relates to a small project to deliver a training and development activity:...
Q3. The following information relates to a small project to deliver a training and development activity: Activity Duration (Weeks) Predecessor(s) A Select personnel 3 - B Invite personnel 5 - C Check budget 14 A D Prepare materials 5 A E Select instructor 4 B F Select date and venue 7 B G Remind personnel 8 D, E H Deliver training 5 G, F a. Draw the network diagram. b. Find the critical path and expected duration. c. Assume activity...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3 3 9 C -- 6 10 14 D A, B 3 5 7 F C 6 8 13 G D, E 2 4 6 H F 3 3 9 Calculate the probability that the project will be completed in less than 25 weeks. NOTE NO need to draw the network diagram on this page,   It...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable...
A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 6 8 10 B A 1 2 4 C A 9 12 15 D A 3 4 5 E B 4 6 7 F B 14 16 22 G C, D 2 3 4 H E, G 1 2 3 I G 6 8 9 J H, I 4 6 8 K F, H, J 1 2 5 a. Draw the...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...