Question

In: Operations Management

The table below presents durations, direct costs and immediate predecessors for each activity of a project...

The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40.

Activity Code

Immediate Predecessors

Normal Duration (week)

Normal Total Direct Cost (L.E)

Crash Duration (Week)

Crash Total Direct Cost (L.E)

Total Allowable crash Time (Week)

Cost Slope per Week

(L.E)

A

None

8

325

5

400

3

25

B

None

12

1200

11

1320

1

120

C

None

14

900

14

900

0

0

D

A

7

520

5

600

2

400

E

B,D

5

210

4

270

1

60

F

B

8

100

7

190

1

90

G

E

5

200

4

250

1

50

H

C,F

3

300

2

400

1

100

The Critical Path is A-D-E-G = 25 week

If the contract entitles the contracting company L.E. 80 for each week below the 26-week contract duration limit, Calculate the optimum project completion time?

Solutions

Expert Solution


Related Solutions

19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity...
1) In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST and EFT for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.) 2)In a project, activity A, B, and C are the successors...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2...
Activity Code Immediate Predecessors Activity Duration (Week) A None 3 B A 3 C A 2 D C 2 E B&C 3 F B 2 G D&E 1 H G 4 I F 7 J H&I 2 K J 4 L F 6 Activity Code Early Start Early Finish Late start Later Finish Total Float A 0 3 0 3 0 B 3 6 3 6 0 C 3 5 5 7 2 D 5 7 8 10 3 E...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT