Question

In: Operations Management

The estimated times and immediate predecessors for activities in a project are given below in the...

The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent.

Task                           Predecessor                Optimistic   Most Likely   Pessemistic    

                                                                        Time (wks)    time (wks)     time (wks)

Architectural design                            --         10                  30                    45

Software                      Architectural design    13                  15                    23

Compilg                      Software                          2                  3                    4

Hardware                    Architectural design    15                  20                    25

Integration                   Software & Hardware   20                  22                    24

Bug fixes                     Integration                   3                    4                      11

           

a) Draw an activity-on-node network diagram for this project.

b) Identify the critical path and estimate the expected time to complete the project.

c) What is the probability of finishing this project in 77 weeks?

Solutions

Expert Solution

If you liked the answer please give an Up-vote, this will be quite encouraging for me, thank you!


Related Solutions

The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table.
The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent. a) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network? b) What is the variance of the critical path? What is the variance of the other path in the network? What is the project duration (in weeks)? c)...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each...
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1 1 1...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 1 3 5 C A 2 5 11 D A 1 8 9 E B 1 2 3 F C,D 1 6 11 G D,E 1 2 3 H F,G 2 3 3 b. What is the critical path? B-E-G-H A-C-F-H A-D-F-H A-D-G-H c. What is the expected project completion time? (Round your answer...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated...
Problem 1 A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Immediate Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) A -- 1 2 3 B -- 2 3 4 C -- 3 4 5 D A 4 5 12 E B 1 3 5 F B 3 4 11 G C 5 6 13 H D, E 8 9 10 I F, G 4 5 6 J H, I 1...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...