The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent.
Task Predecessor Optimistic Most Likely Pessemistic
Time (wks) time (wks) time (wks)
Architectural design -- 10 30 45
Software Architectural design 13 15 23
Compilg Software 2 3 4
Hardware Architectural design 15 20 25
Integration Software & Hardware 20 22 24
Bug fixes Integration 3 4 11
a) Draw an activity-on-node network diagram for this project.
b) Identify the critical path and estimate the expected time to complete the project.
c) What is the probability of finishing this project in 77 weeks?