Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...

Suppose there are 8 activities in your project with the following information.

Activity

Immediate Predecessor

Processing Time

(days)

Processing

Cost

($ per day)

A B 5 20
B - 4 40
C A,B 6 30
D A 7 10
E C,D 6 25
F C 5 40
G E,F 4 25
H F 3 50

What is the total project lead time?

a.) 40 b.)26 c.) 23

What activity is not part of the critical path?

a.) activity E b.) Activity C c.)Activity D

If activity F does not start once it is ready, but it is late for 3 days. What will happen to the project lead time?

a.)Will be 2 days delay b.)Does not change c.)Will be 1 day delay

If activity E does not start once it is ready, but it is late for 2 days. What will happen to the project lead time?

a.)Does not change b.)Will be 1 day delay c.)Will be 2 days delay

Solutions

Expert Solution

Below is the calculation of ES, EF, LS & LF -

Activity IP Processsing (Days) ES EF LS LF Slack
B - 4 0 4 0 4 0
A B 5 4 9 4 9 0
C A,B 6 9 15 10 16 1
D A 7 9 16 9 16 0
E C,D 6 16 22 16 22 0
F C 5 15 20 17 22 2
G E,F 4 22 26 22 26 0
H F 3 20 23 23 26 3

Below is the screenshot of the formula applied -

Below is the answer ot the question basis above calculated result -

What is the total project lead time - b.)26

What activity is not part of the critical path- b.) Activity C

If activity F does not start once it is ready, but it is late for 3 days. What will happen to the project lead time - c.)Will be 1 day delay (Since F has a slack of 2 days hence 3 days delay will dekay the project by 1 days (3-2 = 1 day)

If activity E does not start once it is ready, but it is late for 2 days. What will happen to the project lead time - c.)Will be 2 days delay (Activity delay will delay the project by 2 day as it has 0 slack)


Related Solutions

From Q1: Suppose there are 8 activities in your project with the following information. Activity Immediate...
From Q1: Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 Base on the information of the project in question 1, you monitor the status of the project at the end of day 18...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time...
A public accounting firm requires the following activities for an audit: Activity Immediate Predecessor Activity time A - 3 B A 2 C - 5 D B, C 2 E A 4 F B, C 6 G E, D 5 Draw a network for this project? (Marks 0.5) Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 0.5) What are the critical path? (Marks 0.5)
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8...
You are given the following table Activity a m b Immediate Predecessor A 2 5 8 - B 5 7 9 - C 2 4 6 - D 1 2 3 A E 1 4 7 C F 3 6 9 B,D,E G 1 5 9 F H 1 2 3 F I 2 5 8 G,H Draw an AON network based on the given table Determine the expected time for each activity Calculate the ES, EF, LS, LF for...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT