Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...

Suppose there are 8 activities in your project with the following information.

Activity

Immediate Predecessor

Processing Time

(days)

Processing

Cost

($ per day)

A B 5 20
B - 4 40
C A,B 6 30
D A 7 10
E C,D 6 25
F C 5 40
G E,F 4 25
H F 3 50

What is the total project lead time?

a.) 40 b.)26 c.) 23

What activity is not part of the critical path?

a.) activity E b.) Activity C c.)Activity D

If activity F does not start once it is ready, but it is late for 3 days. What will happen to the project lead time?

a.)Will be 2 days delay b.)Does not change c.)Will be 1 day delay

If activity E does not start once it is ready, but it is late for 2 days. What will happen to the project lead time?

a.)Does not change b.)Will be 1 day delay c.)Will be 2 days delay

Solutions

Expert Solution

Below is the calculation of ES, EF, LS & LF -

Activity IP Processsing (Days) ES EF LS LF Slack
B - 4 0 4 0 4 0
A B 5 4 9 4 9 0
C A,B 6 9 15 10 16 1
D A 7 9 16 9 16 0
E C,D 6 16 22 16 22 0
F C 5 15 20 17 22 2
G E,F 4 22 26 22 26 0
H F 3 20 23 23 26 3

Below is the screenshot of the formula applied -

Below is the answer ot the question basis above calculated result -

What is the total project lead time - b.)26

What activity is not part of the critical path- b.) Activity C

If activity F does not start once it is ready, but it is late for 3 days. What will happen to the project lead time - c.)Will be 1 day delay (Since F has a slack of 2 days hence 3 days delay will dekay the project by 1 days (3-2 = 1 day)

If activity E does not start once it is ready, but it is late for 2 days. What will happen to the project lead time - c.)Will be 2 days delay (Activity delay will delay the project by 2 day as it has 0 slack)


Related Solutions

From Q1: Suppose there are 8 activities in your project with the following information. Activity Immediate...
From Q1: Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 Base on the information of the project in question 1, you monitor the status of the project at the end of day 18...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT