Question

In: Operations Management

From Q1: Suppose there are 8 activities in your project with the following information. Activity Immediate...

From Q1:

Suppose there are 8 activities in your project with the following information.

Activity

Immediate Predecessor

Processing Time

(days)

Processing

Cost

($ per day)

A B 5 20
B - 4 40
C A,B 6 30
D A 7 10
E C,D 6 25
F C 5 40
G E,F 4 25
H F 3 50

Base on the information of the project in question 1, you monitor the status of the project at the end of day 18 and found out the following information.

Activity % Work Completion Incurred Cost
A 100% $100
B 100% $160
C 100% $180
D 100% $80
E 17% (equivalent to 1 day of work) $40
F 20% $50
G - -
H - -

Problem1: What is the closest number to the planned value of this project?

A.)$575 B.)$610 C.)$620

Problem2: From the information above, what is the closest number to the earned value of this project?

A.)$610 B.)$620 C.)$575

Problem3 :From the above information, what is the performance of this project?

A.)Right on the budget B.)Over budget by 5.7% C.)Over budget by 7.2%

Problem4: From the above information, what is the performance of this project in term of schedule?

A.)Behind schedule by 7.2% B.)Behind schedule by 5.7% C.)Right on schedule

Problem5 :Suppose the behavior of the cost is likely to continue this trend, what is the new estimation of cost at the end of the project?

A.)$1,177 B.)$1,145 C.)$1,197

Problem6 :Suppose the behavior of the cost up to the monitoring date is unusual, and the management can fix it and all the cost will likely to be as plan, what is the new estimation of cost at the end of the project?

A.)$1,145 B.)$1,177 C.)$1,197

Solutions

Expert Solution

Budget is the row-wise sum up to Day-26

PV is the row-wise sum up to Day-18

EV = Budget * % complete

-------------------

A) PV = $620

Actually PV is coming at $680. But no such option is given, so we select $620 which is the closest (there must be some flaw in the question set - check that).

B) EV = $575

C) Over-budget by 5.7%

% overbudget = (AC - EV) / AC = (610 - 575) / 610 = 5.7%

D) Behind schedule by 7.2%

% behind schedule = (PV - EV) / PV = (620 - 575) / 620 = 7.2%

E) $1177

CPI = EV / AC = 575 / 610 = 0.9426

EAC = AC + (BAC - EV) / CPI = 610 + (1110 - 575) / 0.9426 = 1177

F) $1145

EAC = AC + (BAC - EV) = 610 + (1110 - 575) = 1145


Related Solutions

Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT