Question

In: Computer Science

Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...

Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path is the critical path.

Figure 1:

(a) Formulate the network flow model for the corresponding diagram.

(b) What is the logical resoning behind the fact that the longest path in a network is chosen to be the critical path.


Solutions

Expert Solution

Decision variable:

Xij­ = 1, the arc from node i to node j is chosen in the optimal (longest) path otherwise Xij­ = 0

Objective Function:

Maximize the total time required from node 1 to node 9:

Max. Z = ∑(cij)(Xij)

Where, cij = time taken by arc (activity) from ith node and jth node
MAx Z. = 5X12 + 3X13 + 3X35 + 2X25 + 4X24 + 4X47 + 1X46 + 2X58 + 6X57 + 6X57 + 5X69 + 4X79 + 7X89

Constraint:

For longest route problem, following constraint are to be satisfied,

For origin Node 1, outgoing arc is equal to 1,

X12 + X13 = 1

For intermediate nodes,

Arc in = arc out

For node 2: X12 = X25 + X24 or X12 – X25 - X24 = 0  

For node 3: X13 = X35 or X13 – X35 = 0

For node 4: X24 = X46 + X47 or X24 – X46 – X47 = 0

For node 5: X25 + X35 = X57 + X58 or X25 + X35 - X57 - X58 = 0

For node 6: X46 = X69 or X46 – X69 = 0

For node 7: X57 + X47 = X79 or X57 + X47 – X79 = 0

For node 8: X58 = X89 or X58 – X89 = 0

For destination node:

Arc in = 1

For node 9, X69 + X79 + X89 = 1


Related Solutions

Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project....
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project. b. Determine the critical path using the expected time for each activity (you can use Excel), and the expected project duration. c. What is the probability that the project will be finished in 3 weeks? In 4 weeks? Time estimates (days) Activity Predecessor a m b a -- 1 3 5 b -- 2 3 5 c -- 2 4 7 d a 1...
Section C. Arc Consistency Consider the following constraint network. 10. If the variables A, B and...
Section C. Arc Consistency Consider the following constraint network. 10. If the variables A, B and C each have the domain {1,2,3,4} before arc consistency is run, indicate what their domains will be after arc consistency has finished: A = {               } B = {    } C = {                         } 11. If we have just considered the edge <B, A < B> and reduce the domain of B as a result, do we need to add any arcs back to...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
Q3-Compartmentalization. The project must be compartmentalized into a number of manageable activities and tasks. Why?
Q3-Compartmentalization. The project must be compartmentalized into a number of manageable activities and tasks. Why?
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing...
Suppose there are 8 activities in your project with the following information. Activity Immediate Predecessor Processing Time (days) Processing Cost ($ per day) A B 5 20 B - 4 40 C A,B 6 30 D A 7 10 E C,D 6 25 F C 5 40 G E,F 4 25 H F 3 50 What is the total project lead time? a.) 40 b.)26 c.) 23 What activity is not part of the critical path? a.) activity E b.)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT