Question

In: Operations Management

Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project....

Consider the project described in the below Excel

a. Construct an Activity-on-Node network for the project.

b. Determine the critical path using the expected time for each activity (you can use Excel), and the expected project duration.

c. What is the probability that the project will be finished in 3 weeks? In 4 weeks?

Time estimates (days)
Activity Predecessor a m b
a -- 1 3 5
b -- 2 3 5
c -- 2 4 7
d a 1 3 4
e d 2 5 8
f b,e 1 2 2
g b,c,e 3 6 8
h f 2 4 5
i g 3 4 6
j h,i 1 2 4

Solutions

Expert Solution

a)

b) Time of completion: 23 days

Critical path


Related Solutions

Consider the project described in the below Excel a. Use Excel to find the critical path...
Consider the project described in the below Excel a. Use Excel to find the critical path and the project duration using normal activity times. b. What is the shortest duration the project can be crashed down to? c. If you were to crash the project manually and your goal is to minimize crashing cost, which activity would you start with? d. Find the cheapest way to crash the project to 33 weeks. What are the critical activities in the crashed...
Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all...
Question 01: Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity L....
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days.
Supplemental assignment for MGMT8300: Network Diagram and the Critical Path 1. Draw an Activity on Arrow (AOA) network diagram based on the following table. The network proceeds from node 1 to node 1. 9. All times are in days. 2. What is the critical path? 3. How long will it take to complete the project if everything goes according to plan? 4. Choose an activity that is not on the critical path. How many days longer should it take in order for the critical...
Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
Construct an AoA network for the 'Project Infiltration', and explain how the activities,events and symbols are...
Construct an AoA network for the 'Project Infiltration', and explain how the activities,events and symbols are applied. Identify and briefly different techniques which you have considered to use in order to draw the AoN network for 'Project Infiltration'. Calculate the total duration of 'Project Infiltration'. Calculate the different forward and backward passes. Calculate the float/slack of 'Project Infiltration'. Explain the critical path of 'Project Infiltration', and ensure that the reader understands the importance of the critical path.
A node is A computer on a blockchain network A type of cryptocurrency A blockchain An...
A node is A computer on a blockchain network A type of cryptocurrency A blockchain An exchange
Explain the logic used to determine which activity to reduce on a Project Network based on...
Explain the logic used to determine which activity to reduce on a Project Network based on the cost slope and other relevant information.
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...