Question

In: Computer Science

Q3-Compartmentalization. The project must be compartmentalized into a number of manageable activities and tasks. Why?

Q3-Compartmentalization. The project must be compartmentalized into a number of manageable activities and tasks. Why?

Solutions

Expert Solution

Compartmentalization basically means the division of something into sections or categories.

In managing any complex Project Compartmentalization acts as a vital skill. The complexity of a software system (or any complex project) can be manage by compartmentalize it into small tasks.

    Compartmentalization hide some details so you don’t have to think about them all the time. We can only keep a small number of things in our head at one time. For e.g , The project can contain many sub parts and all parts cannot be understand at once. We have to work on each sub parts individually so we can understand it as whole.

Advantages of Compartmentalization

1) Tasks can be assigned to a specific members of the software team.

2) Interdependent tasks are accomplished first. Certain tasks occur in sequence whereas other tasks occur in parallel. Therefore tasks which occur in sequence has to be performed in a sequential order since the output of one task will be the input of the next task. Other tasks can occur independently.

3) Start date and a completion date can be identified based on whether the work will be performed in a full time or part time basis.

Please Rate the answer and if you have any query please ask .


Related Solutions

Assume that for this project to be completed, five independent tasks must be completed. These tasks...
Assume that for this project to be completed, five independent tasks must be completed. These tasks are proceeding in parallel by five different subcontractors. To keep it simple, let's assume that each task takes between 1 and 5 months to complete (uniformly distributed, i.e. equally likely to take any amount of time between 1 and 5 months). So, the mean time to complete each task is 3 months and the probability of any given task taking 3 months or longer...
Consider the following activity-on-arc project network, wherethe 12 arcs (arrows) represent the 12 activities (tasks)...
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path...
A project has four activities (A, B, C, and D) that must be performed sequentially. The...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.32 6 0.39 7 0.27 8 0.02 B 4 0.18 6 0.51 8 0.31 C 7 0.10 9 0.29 11 0.43 13 0.15 15 0.03 D 10 0.61 12 0.39 Provide the base-case, worst-case, and best-case calculations for the time to complete...
Record the following transactions in the journal of Capital Project Fund and Governmental Activities. (You must...
Record the following transactions in the journal of Capital Project Fund and Governmental Activities. (You must prepare the journal form using Excel) 1. A capital projects fund issued $10,000,000, 5 percent bonds for $10,100,000 to finance the construction of a little league baseball park. Premiums received are to be used to service the debt issue. 2. The Parks and Recreation Special Revenue Fund transferred $300,000 for use in construction. 3. A construction contract was awarded in the amount of $10,200,000....
Q3. Why regulators must enforce efficiency in financial markets Q4. Draw figures to show the government,...
Q3. Why regulators must enforce efficiency in financial markets Q4. Draw figures to show the government, foreign, and households demand for loanable fund Q5. LMB Inc. wants to issue 365-day commercial paper. One year T-bills currently have a yield of 6 percent. Assume that a default risk premium of 1.65 percent, a liquidity premium of 0.15 percent, and a 0.35 percent tax adjustment are necessary to sell the commercial paper to investors. What is the appropriate yield the company should...
Discuss what needs to be done as part of closing a project. Why are these activities...
Discuss what needs to be done as part of closing a project. Why are these activities important? Discuss the internal post project evaluation process and the two types of meetings involved List several questions that you would ask during a post-project evaluation and describe changes that you would make in your next project to improve based upon possible responses to the questions.
Discuss what needs to be done as part of closing a project. Why are these activities...
Discuss what needs to be done as part of closing a project. Why are these activities important? Discuss the internal post project evaluation process and the two types of meetings involved. What are some ways you can obtain feedback from a customer after a project has been completed? How would you use this information? Why are some projects terminated before they are completed? When would it be wise to do so? List the several lessons learned from a project in...
The table below defines number of working activities needed to accomplish a House project. The relationships...
The table below defines number of working activities needed to accomplish a House project. The relationships or dependencies between predecessors and successors activities are all defined as "finish to start" type. Dependency Duration in days I.D Activity name ................................ 20 A Excavation work A 5 B Plain concrete work A 6 C Reinforced concrete work B & C 2 D Install grass C 10 E Build walls E 8 F Build roof E 7 G Plaster work F & G...
A project has five activities: A, B, C, and D, which must be carried out sequentially....
A project has five activities: A, B, C, and D, which must be carried out sequentially. The probability distributions of the number of weeks required to complete each of the activities A, B, and C are uniform in intervals [1,5], [2,3], and [3,6], respectively. The number of weeks required to complete activity D is a beta distribution with shape parameters a=2 and b=5, lower bound 2, and upper bound 10. Use simulation to forecast the total completion time of the...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 3 0.29 4 0.38 5 0.29 6 0.04 B 7 0.22 9 0.53 11 0.25 C 9 0.05 11 0.24 13 0.36 15 0.19 17 0.16 D 10 0.59 12 0.41 Provide the base-case, worst-case, and best-case calculations for the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT