Question

In: Operations Management

Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?

Critical Path Network: 

image.png

 a. Develop the critical path network.

 b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?

 d. What are the slack time of the activities?

 e. What is the completion time of the project?

 f. What are the expected times of the activities?

 g. What is the project variance?

 h. What is its standard deviation?


Solutions

Expert Solution

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

3

0

3

1

4

1

B

4

0

4

0

4

0

C

2

3

5

6

8

3

D

4

4

8

4

8

0

E

6

8

14

8

14

0

FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH & COMPLETION TIME

B + D + E = 14

PERT ANALYSIS

ACTIVITY OPTIMISTIC a MOST LIKELY m PESSIMISTIC b EXPECTED VARIANCE
(a + (4m) + b) / 6 ((b - a) / 6) ^ 2
A 2 3 4 3 0.11
B 3 4 6 4 0.25
C 1 2 4 2 0.25
D 3 4 6 4 0.25
E 4 5 8 5 0.44

VARIANCE OF CRITICAL PATH = 0.25 + 0.25 + 0.44 = 0.94

STDEV OF CRITICAL PATH = SQRT(VARIANCE) = SQRT(0.94) = 0.9695


Related Solutions

Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS,...
Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS, LF, TF and FF for each activity. Which activities in the project are on the critical path Activity Duration IPA Type of relationship Lag A 4 B 3 C 8 A D 7 A, B E 6 D SS 3 F 3 D G 5 F SS FF 2 Note: If the relationship type is not mentioned, it is FS. If no lag/lead is...
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
What is the critical path of the network?
What is the critical path of the network?
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Build the network and determine the critical path.
Build the network and determine the critical path.
Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities...
Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities on a critical path have a float of zero. C. A delay in critical activity surely delays the completion of project. D. A network can have more than one critical path. E. Each critical activity has identical earliest and the latest start times.
In the Critical Path Method network diagram, what is unique about the early start and early...
In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?