Question

In: Computer Science

In the Critical Path Method network diagram, what is unique about the early start and early...

In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?

Solutions

Expert Solution

First we will need to understand what is critical path method by a brief explanation to give answer of your questions:

Critical Path Method is a techqnique to plan schedules timeline of various kinds of projects belonging to construction, IT, research etc. In this we have sequence of activities which has to be done one after another from start to end of the project which form a network path.

Critical Path : In the network of activities ,the longest duration of a path is known as critical path. Any delay in this path will lead to the delay in whole project.

Early Start and Early Finish

We use forward pass to find early start and early finish and start from beginning to the end. The formula is given by :

  • Early Start of the activity = Early Finish of predecessor activity + 1
  • Early Finish of the activity = Activity duration + Early Start of activity – 1

Now we will understand what is unique about early start and early finish:

To know how much freedom we have in our schedule we calculate early start and early finish. After calculating this you will get to know about how much you can move your start dates for an activity without causing delay. For example if early start and finish for an activity is 7 and 15 respectively while late start and late finish for an activity is 12 and 20 respectively, now you can see that even if you start after 7 but before 12, you can still be on time to complete the activity.


Related Solutions

about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
What is the critical path of the network?
What is the critical path of the network?
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Build the network and determine the critical path.
Build the network and determine the critical path.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
Using the provided network diagram, write a program in c ++ that finds the shortest path...
Using the provided network diagram, write a program in c ++ that finds the shortest path routing using the Bellman-Ford algorithm. Your program should represent the fact that your node is U. Show how the iterative process generates the routing table for your node. One of the keys to your program will be in determining when the iterative process is done. Deliverables 1. Provide an output that shows the routing table for your node after each iteration. Add a second...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT