Question

In: Civil Engineering

Draw the following network, Draw the precedence Network for the following project Find ES, EF, LS,...

Draw the following network,

  1. Draw the precedence Network for the following project
  2. Find ES, EF, LS, LF, TF and FF for each activity.
  3. Which activities in the project are on the critical path

Activity

Duration

IPA

Type of relationship

Lag

A

4

B

3

C

8

A

D

7

A, B

E

6

D

SS

3

F

3

D

G

5

F

SS

FF

2

Note: If the relationship type is not mentioned, it is FS. If no lag/lead is mentioned, it is zero.

Solutions

Expert Solution

a). The precedence network or the A-O-N diagram for the project is drawn. (Image 2; see the legend ).

b).ES, EF, LS, LF, TF and FF for each activity is found (see the legend to understand it clearly ).

All the critical path calculations are tabulated.

Free float,FF = ES of successor activity - EF of current activity.

Total float, TF = LF - EF or LS - ES.

c). Critical activities are A, D, F and G.

(Please give a thumbs up ).


Related Solutions

Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each...
Question 1 a. Draw a precedence diagram for the following fabrication of steel project. For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the critical path. Activity Immediate Predecessor Duration (weeks) A None 2 B A 4 C A 2 D B 2 E B, C 4 F A, E 6 G D 4 H D, E, F 2 I G, H 6 J H, F 6 K...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.   Activity Duration mobilize 1 remove siding 4 excavate/form slab 7 place slab 4 set support beam 1 stud wall up 6 install siding 4 install windows 5 set raffers 4 install roof 6 finish trim 4 paint siding 7 move out 1
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate...
A project has the following activities, precedence relationships, and time estimates in weeks: ​ Activity Immediate Predecessor Activities Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) A — 15 20 25 B — 8 10 12 C A 25 30 40 D B 15 15 15 E B 22 25 27 F E 15 20 22 G D 20 20 22 ​ a.   Compute the expected time and variance for each activity. b.   Determine the critical path and the expected...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence relationships (be sure to use the triple time estimate). All times are in days: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 6 --- B 5 7 10 --- C 2 3 11 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6...
A project for improving a billing process has the following precedence relationships and activity​ times: Using...
A project for improving a billing process has the following precedence relationships and activity​ times: Using the info below calculate the slack for each activity. Which activities are on the critical path?                                                                                                           Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 5 ---- B 10 ----- C 6 A D 14 ​B, C E 9 B F 5 D G 3 E H 6 ​F, G
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors...
A project consisting of six activities has the following precedence constraints. Activity Time (weeks) Immediate Predecessors A 3 B 3 A C 4 A D 5 A E 6 C, D F 2 B, E Draw the AOA (activities on the arrows) network diagram for this project
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
Which of the following proteins does not bind GTP? EF-Tu EF-G IF-2 Phosphohexose Isomerase
Which of the following proteins does not bind GTP? EF-Tu EF-G IF-2 Phosphohexose Isomerase
Find a real financial market event/anomaly that caused by behavioral bias(es) and respond to the following...
Find a real financial market event/anomaly that caused by behavioral bias(es) and respond to the following questions: 1. Provide detailed background information of the event or describe details of the anomaly (such as asset mispricing) 2. Discuss the possible behavioral bias(es) that might affect corporate/investors’ decisions in the event/anomaly 3. Propose a strategy for correcting the bias(es) or taking advantage of this anomaly (making profit).
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT